TTK. Installation of metal air ducts for internal ventilation systems

Typical flow chart for installation and
mounting internal systems ventilation and
air conditioning with supply and exhaust
installations and equipment systems
refrigeration

Typical technological map
(TTK)

Project code: 1012/40

Explanatory note

2012 r.

1. GENERAL DATA

This technological map is designed for the installation and installation of internal ventilation and air conditioning systems with air handling units and equipment for refrigeration systems in industrial, administrative, public and residential buildings.

The technological map was drawn up taking into account the requirements of the following regulatory documents:

Air ducts made of thin sheet roofing steel with a diameter and size of the larger side up to 2000 mm, should be made:

Spiral-lock or longitudinal seam on rebates;

Spiral welded or longitudinal welded.

Air ducts made of thin sheet roofing steel with a side size of more than 2000 mm should be made panel (welded, glue-welded).

Air ducts from metal-plastic should be made on folds, and from of stainless steel, titanium, as well as from sheet aluminum and its alloys - on folds or on welding.

Air ducts made of sheet aluminum and its alloys with a thickness of up to 1.5 mm should be performed on folds, with a thickness of 1.5 to 2 mm - on folds or welding, and with a sheet thickness of more than 2 mm - on welding.

Longitudinal folds on air ducts made of thin-sheet roofing and stainless steel and sheet aluminum with a diameter or size of a larger side of 500 mm or more must be fixed at the beginning and end of the duct link spot welding, electric rivets, rivets or bulging.

Folds on air ducts with any metal thickness and manufacturing method must be cut-off.

The end sections of the seam seams at the ends of the air ducts and in the air distribution openings of the metal-plastic air ducts must be fixed with aluminum or steel rivets with an oxide coating, ensuring operation in aggressive environments specified in the working documentation.

Seam seams should have the same width along their entire length and be evenly and tightly upset.

In rebated air ducts, as well as in cutting plans, there should be no cross-shaped joints of seams.

On straight sections of rectangular air ducts with a side cross-section of more than 400 mm, it is necessary to constructively perform rigidity in the form of bends (ridge) with a step of 300 - 500 mm along the perimeter of the air duct or diagonal bends (ridge). If the side is more than 1000 mm and the length is more than 1000 mm, in addition, it is necessary to install external stiffening frames, with a step of no more than 1250 mm. Stiffening frames must be securely fixed by spot welding, rivets or self-tapping screws.

Stiffening frames should be installed on metal-plastic air ducts using aluminum or steel rivets with an oxide coating, ensuring operation in aggressive environments defined by the working documentation.

Elements of fittings should be connected to each other on zigzags, folds, welding, rivets.

Elements of fittings made of metal-plastic should be connected to each other on the folds.

Zig joints for systems transporting air of high humidity or with an admixture of explosive dust are not allowed.

The connection of the sections should be performed:

for round air ducts in a flangeless way (nipple / sleeve), shroud connection or on flanges;

for rectangular ducts: busbar (large / small) or on flanges. The connections must be strong and tight.

Fastening the tire to the air duct should be done with rivets with a diameter of 4 - 5 mm, self-tapping screws (in the absence of fibrous components in the moving medium), spot welding, bulging every 200 - 250 mm, but not less than four. The inner corners of the tire should be filled with sealant.

Fastening of flanges to air ducts should be carried out by flanging with a persistent ridge, by welding, spot welding, on rivets with a diameter of 4 - 5 mm or self-tapping screws (in the absence of fibrous components in the transported medium), placed every 200 - 250 mm, but not less than four.

Regulating devices (dampers, throttle valves, dampers, regulating elements of air distributors, etc.) must be easy to close and open, as well as be fixed in a given position.

Air ducts made of non-galvanized steel, their connecting fasteners (including inner surfaces flanges) must be primed (painted) at the procurement company in accordance with the working documentation. The final painting of the outer surface of the air ducts is carried out by specialized construction organizations after their installation.

Ventilation blanks must be completed with parts for their connection and fastening means.

2.2. Preparatory work

2.2.1. General Provisions

Rice. 1. Slings

a - lightweight sling with loops; b - lightweight sling with hooks;
в - four-branch sling

The load to be lifted should be kept from rotating by braces from hemp ropes with a diameter of 20 - 25 mm or braces from steel ropes with a diameter of 8 - 12 mm. For horizontal elements of ventilation systems (enlarged units of air ducts), two guys should be used, for vertical ones (sections of air conditioners, roof fans, air ducts, etc.) - one.

The most common slinging methods are shown in fig. -.

Rice. 2. Slinging VPA-40

Rice. 3. Slinging of an autonomous air conditioner KTR-1-2.0-0.46

Rice. 4. Slinging of radial (centrifugal) fans of version No. 1

Rice. 5. Slinging of fans Ts4-70 No. 6 - 8 version No. 1

Rice. 6. Slinging of fans Ts4-70 No. 6 - 8 version No. 6

Rice. 7. Slinging of fans Ts4-70 No. 10, 12.5

Rice. 8. Slinging the air duct

For the entire installation period, areas for storing air ducts must be equipped.

The device of an on-site air duct warehouse must meet the following basic requirements:

Be located near access roads or railways;

The boundaries of the warehouse must be at least 1 m from the road;

To be at the minimum distance from the installation object, if possible, in the area of ​​the tower crane;

Do not interfere with the production of construction and installation works;

Air duct storage areas should be carefully planned with a slope of 1 - 2 ° to drain surface water, covered with drainage sand or gravel, and, if necessary, have ditches;

Passages, driveways and loading and unloading areas must be cleared of debris, construction waste (in winter - from snow and ice) and sprinkled with sand, slag or ash;

Storage of ventilation equipment must be organized in compliance with the requirements of work safety and fire protection;

At the corners of the open warehouse, protective posts should be installed, warning signs for drivers of vehicles and signs with the name of the installation department or the site and the location of the receiver of goods should be posted;

The warehouse needs to be lit.

Warehousing and storage of air ducts must be organized in accordance with applicable standards and in compliance with the following requirements:

Rectangular air ducts must be stacked; straight sections with a height of no more than 2.7, shaped parts - no more than 2 m;

Circular air ducts should be installed vertically;

Air ducts delivered in inventory containers should be stored in these containers at specially organized container yards. It is prohibited to store air ducts and other products in railway containers;

During storage, each air duct should be laid on wooden inventory pads;

Air ducts in stacks should be placed taking into account the sequence of installation: stacks and containers - provided with signs;

Passages with a width of at least 1 m must be left between the stacks; every three stacks, driveways for vehicles with a width of 3 m should be arranged.

The movement of air ducts along the floors of multi-storey buildings is carried out using lifting equipment or manual transport.

2.3. Works of the main period. Mounting

2.3.1. Installation of internal ventilation and air conditioning systems. General Provisions

Installation of internal ventilation and air conditioning systems should be carried out in accordance with the requirements of SP 73.13330.2012, SP 48.13330.2011, SNiP 12-03-2001, SNiP 12-04-2002, standards and instructions of equipment manufacturers, as well as in accordance with fire safety requirements of SP 7.13130.2009.

Installation must be carried out by industrial methods from air duct assemblies and equipment supplied as a complete set of large blocks.

Installation of systems should be carried out when the facility is ready for construction (seizure) in the amount of:

For industrial buildings- the entire building with a volume of up to 5000 m 3 and a part of the building with a volume of over 5000 m 3;

For residential and public buildings up to five floors - a separate building, one or more sections; over five floors - five floors of one or more sections.

Another scheme of installation organization is possible, depending on the adopted constructive scheme.

2.3.2. Installation of air ducts

The method of installation of air ducts should be selected depending on their position (horizontal, vertical), location relative to structures (near the wall, near columns, in the interfarm space, in the shaft, on the roof of the building) and the nature of the building (one- or multi-storey, industrial, public and etc.).

As fittings complex geometric shape, as well as for connection of ventilation equipment, air distributors, silencers and other devices located in false ceilings, chambers, etc., flexible air ducts made of fiberglass SPL, metal fabric, aluminum foil etc. The use of flexible air ducts as straight links is not allowed.

In order to reduce aerodynamic drag, parts from flexible sleeves in the mounted position must have a minimum compression ratio.

Installation of metal air ducts should be carried out, as a rule, in enlarged blocks in the following sequence:

Marking of installation sites for fastening means for air ducts;

Installation of fastening means;

Coordination with the builders of the locations and methods of fastening the lifting equipment;

Delivery of air duct parts to the installation site;

Checking the completeness and quality of the delivered air duct parts;

Assembly of air duct parts into enlarged blocks;

Installation of the unit in the design position and fixing it;

Installation of plugs on the upper ends of vertical air ducts located at a height of up to 1.5 m from the floor.

The length of the block is determined by the dimensions of the section and the type of connection of the air ducts, the conditions of installation and the availability of lifting equipment.

The length of enlarged horizontal air duct units connected on flanges should not exceed 20 m.

Organization diagrams working area when installing air ducts are given in Fig. -.

Rice. 9. Diagram of the organization of the working area during the installation of air ducts
on outside wall building

1 - console with block; 2 - winch; 3 - auto-hydraulic elevator;
4 - traverse; 5 - guy line; 6 - block

Rice. 10. Diagram of the organization of the working area during the installation of horizontal
air ducts in the building

1 - winch; 2 - traverse; 3 - enlarged unit of the air duct; 4 - pendants

2.3.3. Fan installation

The fans must be installed in the following sequence:

Acceptance of ventilation chambers premises;

Delivery of the fan or its individual parts to the installation site;

Installation of lifting equipment;

Slinging the fan or individual parts;

Lifting and horizontal movement of the fan to the installation site;

Fan installation (fan assembly) on supporting structures (foundation, platform, brackets);

Checking the correct installation and assembly of the fan

Fastening the fan to supporting structures;

Checking the fan operation.

During the installation of fans, a step-by-step operational control should be carried out in accordance with the operational control cards.

2.3.4. Installation of equipment for refrigeration systems

When setting up ventilation and air conditioning systems for the design air flow, you should perform:

Check the compliance of the actual design of ventilation and air conditioning systems with the design documentation and requirements SP 73.13330.2012 ;

Testing of fans during their operation in the network, checking the compliance of the actual technical characteristics with the passport data, including: air flow and total pressure, rotation speed, power consumption, etc.;

Checking the uniformity of heating (cooling) of heat exchangers and checking the absence of moisture carryover through the drip catchers of the irrigation chambers or air coolers;

Determination of the flow rate and resistance of dust collecting devices;

Checking the operation of natural ventilation exhaust devices;

Testing and adjusting the ventilation network of systems in order to achieve design indicators for air consumption in air ducts, local suction, for air exchange in rooms and determination of air leaks or losses in systems.

Deviations of air flow rates from those provided for in the design documentation after adjustment and testing of ventilation and air conditioning systems are allowed:

Within ± 8% - in terms of the air flow passing through the air distribution and air intake devices of general ventilation and air conditioning installations, provided that the required backpressure (vacuum) of air in the room is ensured;

Up to +8% - according to the air flow rate removed through local suction and supplied through the spray nozzles.

For each ventilation and air conditioning system, a passport is issued in two copies (Appendix G, SP 73.13330.2012).

2.4.2. Refrigeration testing

Testing of water cooling systems should be carried out with the heat generators and expansion vessels turned off by the hydrostatic method with a pressure equal to 1.5 working pressure, but not less than 0.2 MPa (2 kgf / cm 2) at the lowest point of the system.

The system is recognized as having passed the test if, within 5 minutes of keeping it under test pressure:

The pressure drop will not exceed 0.02 MPa (0.2 kgf / cm 2);

There are no leaks in welds, pipes, threaded connections, fittings and equipment.

3. REQUIREMENTS FOR QUALITY AND ACCEPTANCE OF WORKS

Quality control of work on the installation of ventilation and air conditioning systems should be carried out by specialists or special services that are part of the construction organization or attracted from outside, equipped with technical means providing the necessary reliability and completeness of control.

Quality control of work is carried out at all stages of the technological chain, starting from the development of the project and ending with its implementation at the facility on the basis of PPR and flow charts. Quality control should include incoming control of working documentation, structures, products, materials and equipment, operational control of individual assembly processes or production operations and assessment of the conformity of the work performed.

At input control working documentation is checked for completeness and sufficiency of the technical information contained in it for the production of work.

During the incoming inspection of products, materials and equipment, it is checked by external examination that they comply with the requirements of standards or other regulatory documents and working documentation, as well as the presence and content of passports, certificates and other accompanying documents.

3.1. Requirements for the quality of work on the installation of air ducts

Air ducts should be installed in accordance with design references and elevations. The connection of the air ducts to the technological equipment must be carried out after its installation.

Air ducts intended for transporting humidified air should be installed so that there are no longitudinal seams in the lower part of the air ducts.

Areas of air ducts where dew may fall from the transported humid air, should be laid with a slope of 0.01 - 0.015 towards the drainage devices.

The spacers between busbars or duct flanges must not protrude into the ductwork.

Gaskets should be made of the following materials: foam rubber, tape porous or monolithic rubber with a thickness of 4 - 5 mm, polymer mastic bundle (PMZh) - for air ducts through which air, dust or waste materials move with temperatures up to 343 K (70 ° C) ...

To seal flangeless air duct connections, use:

Sealing tape of the "Guerlain" type - for air ducts through which air moves with a temperature of up to 313 K (40 ° C);

Mastic such as "Buteprol", Silicone and other certified sealants - for circular air ducts with temperatures up to 343 K (70 ° C);

Heat-shrinkable cuffs, self-adhesive tapes - for circular air ducts with temperatures up to 333 K (60 ° C);

Other sealing materials specified in the working documentation.

The bolts in the flange connections must be tightened with all the bolt nuts on the same side of the flange. When installing bolts vertically, the nuts should generally be on the underside of the joint.

Fastening of air ducts should be carried out in accordance with the working documentation.

Fasteners of horizontal metal non-insulated air ducts (clamps, hangers, supports, etc.) on a bandage flangeless connection should be installed:

At a distance of no more than 4 m from one another with circular duct diameters or dimensions of the larger side of a rectangular duct less than 400 mm.

At a distance of no more than 3 m from one another - with diameters of a circular duct or dimensions of the larger side of a rectangular duct of 400 mm or more.

Fasteners of horizontal metal non-insulated air ducts on a flange, nipple (sleeve) connection should be installed at a distance of no more than 6 m from one another:

For circular cross-sections up to 2000 mm diameter,

For rectangular section on flanges, bus on flange connection of circular section with a diameter of up to 2000 mm or rectangular section with dimensions of its larger side up to 2000 mm inclusive.

The distances between the fasteners of insulated metal air ducts of any cross-sectional size, as well as non-insulated air ducts with a circular cross-section with a diameter of more than 2000 mm or a rectangular cross-section with a larger side of more than 2000 mm, should be assigned by working documentation.

The fastening of the nipple (coupling) should be carried out with rivets with a diameter of 4 - 5 mm or self-tapping screws with a diameter of 4 - 5 mm every 150 - 200 mm of a circle, but not less than three.

The clamps should fit tightly around the metal air ducts.

Mounts for vertical metal ducts should be installed at a distance of no more than 4.5 m from one another.

Fastening of vertical metal air ducts inside the premises of multi-storey buildings with a floor height of up to 4.5 m should be carried out in the interfloor ceilings.

Fastening of vertical metal air ducts indoors with a floor height of more than 4.5 m and on the roof of the building should be determined by the working documentation.

Fastening of guy wires and hangers directly to the duct flanges is not allowed. The tension of the adjustable hangers must be uniform.

The deviation of the ducts from the vertical should not exceed 2 mm per 1 m of the duct length.

Freely suspended air ducts should be braced by installing double hangers every two single hangers with a suspension length of 0.5 to 1.5 m.

For hangers longer than 1.5 m, double hangers should be installed through each single hanger.

Air ducts should be reinforced so that their weight is not transferred to the ventilation equipment.

Air ducts should generally be connected to fans through vibration-damping flexible inserts made of fiberglass or other material that provides flexibility, density and durability.

Anti-vibration flexible inserts should be installed immediately prior to individual testing.

When making straight sections of air ducts from a polymer film, bends of the air ducts are allowed no more than 15 °.

To pass through the enclosing structures, the air duct made of plastic film must have metal inserts.

Air ducts made of plastic film should be suspended on steel rings made of wire with a diameter of 3 - 4 mm, located at a distance of no more than 2 m from one another.

The diameter of the rings should be 10% larger than the diameter of the duct. Steel rings should be fastened with a wire or plate with a cutout to a supporting cable (wire) with a diameter of 4 - 5 mm, stretched along the axis of the duct and fixed to the building structures every 20 - 30 m.

To exclude longitudinal movements of the duct when it is filled with air polymer film should be pulled until the slack between the rings disappears.

Table 1. Map operational control installation of metal air ducts

Technological process

Controlled indicators

Measuring tool

Control type

Delivery of air duct parts to the installation site

Checking the completeness of the ventilation system (availability of control devices, fasteners, etc.)

Permanent 100%. Visually. Compliance with the picking list, sketches

Marking of installation sites for fixing air ducts

Installation step of fasteners in accordance with SNiP 3.05.01-85

Roulette I= 10 m

Cord

Plumb line M = 200 g

Permanent 100%

Drilling holes in building structures

Drilling depth

Steel meter

Permanent 100%

Installation of fasteners

Fastening strength

Permanent 100%.

Visually

Assembly into enlarged units of parts of air ducts, regulating and air distribution devices at the site

Correctness of assembly in accordance with the project. Tightness of connections

Visually.

Permanent 100%

Ascent to the design level and interconnection of enlarged units of air ducts with preliminary fastening

The position of transverse seams and detachable duct connections relative to building structures. Verticality of risers. Absence of kinks, curvature in straight sections of air ducts

Plumb line M= 200 g

Visually

Permanent 100%

Alignment of the mounted air ducts and their final fixing

The horizontal installation of the air ducts and the observance of the slopes in the distribution sections of the air ducts. Density of coverage of the duct with clamps. Reliability and appearance of fasteners

Metal meter, tape measureI= 10 m, level I= 300 mm

Permanent 100%.

Visually

Connection of air ducts to ventilation equipment

Correct installation of soft inserts (no slack)

Permanent 100%.

Visually

Testing the operation of regulating devices

Smooth operation of regulating devices

Output 100%.

Visually

3.2. Requirements for the quality of work on the installation of fans

Radial fans on vibration bases and on a rigid base, installed on foundations, must be fixed with anchor bolts.

When installing fans on spring vibration isolators, the latter must have a uniform settlement. Vibration isolators do not need to be fastened to the floor.

When installing fans on metal structures, vibration isolators should be attached to them. Elements of metal structures to which vibration isolators are attached must match the corresponding elements of the fan unit frame.

When installed on a rigid base, the fan frame must fit snugly against the sound insulating pads.

The gaps between the edge of the front disc of the impeller and the edge of the inlet pipe of the radial fan, both in the axial and in the radial direction, should not exceed 1% of the impeller diameter.

Radial fan shafts must be installed horizontally (shafts roof fans- vertically), vertical walls of casings centrifugal fans should not be skewed or tilted.

The gaskets for the split fan shrouds should be of the same material as the gaskets for the ductwork of this system.

The motors must be precisely aligned with the installed fans and secured. The axes of the pulleys of electric motors and fans with a belt drive must be parallel, and the center lines of the pulleys must coincide. The belts must be tensioned according to the manufacturer's requirements.

The motor skids must be mutually parallel and level. The support surface of the slide must be in contact over the entire plane with the foundation.

Couplings and belt drives should be protected.

The fan suction opening not connected to the duct must be protected metal mesh with a cell size of not more than 70 × 70 mm.

Table 2. Map of operational control of installation of centrifugal fans

Technological process

Controlled indicators

Measuring tool

Control type

Supply of the fan unit to the installation site

Checking the availability and quality of component parts

Permanent 100%.

Installation of the frame on the stands. Installation of vibration isolators under the frame

The horizontality of the foundation, frame

Level I= 300 mm

Permanent 100%

Installation of fans on a frame with vibration isolators

Pulley vertical, shaft horizontal

Plumb line M= 200 g

Permanent 100%

Assembly of fans on the frame: installation of the fan frame; installation of the lower part of the fan casing; installation of the turbine with fastening of its frame to the frame; installation of the inlet pipe

Fastening strength. Clearance between the edge of the front disc of the impeller and the edge of the inlet. Fastening strength

Ruler

Visually.

Permanent 100%

Installation of the upper part of the casing and connection on the flanges of individual parts of the fan casing

Tightness of the connection

Visually.

Permanent 100%

Adjustment and final fastening of vibration isolators to the frame

Uniform settlement of vibration isolators. The strength of fastening vibration isolators to the frame

Visually.

Permanent 100%

Balancing the turbine before starting

Correct position of the turbine wheel

Permanent 100%.

Visually, testing by hand (when scrolling, the risks should not coincide)

Installing the skid and the electric motor on the skid

Parallelism of the sled. The strength of the fastening of the electric motor to the slide. The strength of the connection between the electric motor and the fan. Parallelism of the axes of the fan and motor shafts. Ease of rotation of the shafts of the fan and electric motor

Level I= 300 mm

Permanent 100%. Visually

Cord

Installing a belt drive on pulleys. Belt drive guard

Coaxiality of grooves for V-belts of fan and motor pulleys. Correct belt tension

Cord (tension of the cord in the plane of the ends of the pulleys), steel meter, testing by hand

Permanent 100%

Connecting air ducts to the fan with the installation of flexible connectors

Tightness of connections. No slack in flexible joints

Visually.

Permanent 100%

Table 3. Map of operational control of installation axial fans

Technological process

Controlled indicators

Measuring tool

Control type

Quality (no mechanical damage), completeness

Permanent 100%.

Visually, compliance with the passport data of the fan and electric motor

Installation of the fan unit on metal brackets. Fan mount

The strength of the supporting structures. Fastening strength of the fan to the supporting structures. Verticality, horizontal

Plumb line M= 200 g

Visually.

Permanent 100%

Checking fan operation

The gap between the ends of the blades and the shells. Correct direction and ease of rotation of the impeller

Ruler

Permanent 100%.

Visual, freehand testing

Table 4. Map of operational control of installation of roof fans

Technological process

Controlled indicators

Measuring tool

Control type

Supply of a fan complete with an electric motor to the installation site

Completeness, quality (no mechanical damage)

Permanent 100%.

Visually, compliance with the passport data of the fan and electric motor

Checking the horizontal position of the cup support flange

Horizontality

Level I= 300 mm

Permanent 100%

Connecting the self-opening valve to the fan

Ease of valve movement

Permanent 100%.

Visual, freehand testing

Installation of the fan casing on the glass with its fastening with anchor bolts

Fastening strength of the fan to the supporting structures. The verticality of the shaft. Ease of rotation of the shafts of the fan and electric motor. Clearance between inlet and impeller

Plumb line M= 200 g

Permanent 100%.

Visual Freehand Testing

Ruler

Permanent 100%

Checking fan operation

Correct direction of rotation of the wheel

Permanent 100%.

Visually (in accordance with the project)

3.3. Requirements for the quality of work on the installation of air conditioners

Air heaters of air conditioners should be assembled on gaskets made of certified material, with a heat resistance corresponding to the temperature of the heating medium. The rest of the blocks, chambers and units of air conditioners should be assembled on gaskets made of tape rubber 3-4 mm thick, supplied with the equipment.

Air conditioners must be installed horizontally. The walls of chambers and blocks should not have dents, distortions and slopes.

The valve blades should turn freely (by hand). In the "Closed" position, a tight fit of the blades to the stops and to each other must be ensured.

Supports of chambers and air conditioner units must be installed vertically.

Flexible air ducts should be used in accordance with the working documentation as fittings of complex geometric shapes, as well as for connecting ventilation equipment, air diffusers, silencers and other devices located in suspended ceilings and chambers.

The use of flexible air ducts as main air ducts is not allowed.

Fastening of fan coil units, door closers, split systems should be carried out in accordance with the recommendations of the manufacturers.

4. REQUIREMENTS FOR SAFETY AND LABOR PROTECTION, ENVIRONMENTAL AND FIRE SAFETY

Mounting ventilation ducts must be carried out in accordance with the requirements of safety, sanitation and occupational health, established by building codes and rules for occupational safety in construction.

Before being admitted to work on the installation of ventilation ducts, the heads of organizations are required to provide training and briefing on occupational safety at the workplace.

Persons at least 18 years of age who have undergone a medical examination without contraindications to work at height, have professional skills, have been trained in safe methods and techniques of work and have received an appropriate certificate are allowed to work at heights.

Individuals (workers and engineers and technicians) at least 18 years of age who have passed a medical examination and recognized as fit for performance of climbing work, having experience of climbing work for at least one year and tariff category not lower than the third.

Workers admitted to climbing work for the first time must work for one year under the direct supervision of experienced workers appointed by order of the organization.

Electric welding works are allowed to persons who have undergone appropriate training, instruction and testing of knowledge of the rules of safe work with registration in a special magazine and having a qualification certificate. Persons with medical contraindications are not allowed to work on electric welding at a height.

Persons at least 18 years of age who have passed a medical examination, trained in the rules of using the tool, labor safety and have an electrical safety group of at least II, and for connecting and disconnecting electric outlets with a group of at least III are allowed to work with an electrified tool. All electrified tools are subject to registration and registration in a special journal. Each copy of the instrument must have a reference number. Monitoring the serviceability and timely repair of electrified tools is assigned to the department of the chief mechanic of the construction organization. Before issuing an electrified tool, it is necessary to check its serviceability (no short circuit to the body, insulation at the supply wires and handles, the condition of the working part of the tool) and its operation at idle speed.

Responsibility for the correct organization of the safe conduct of work at the facility rests with the contractor and the foreman.

The admission of unauthorized persons, as well as drunken workers to the territory of the construction site, to production, sanitary premises and workplaces is prohibited.

Work on the installation of ventilation and air conditioning systems, as well as equipment for refrigeration systems are carried out according to the permit for work in conditions of hazardous and (or) harmful production factors.

Installation should be carried out only if there is a work production project, flow charts or wiring diagrams... In the absence of these documents installation work lead is prohibited.

The procedure for performing the installation, determined by the project for the production of work, must be such that the previous operation completely excludes the possibility of industrial hazards when performing subsequent ones. Installation of air ducts and equipment parts for ventilation, air conditioning and refrigeration systems should, as a rule, be carried out in large blocks using lifting mechanisms.

No people should be under the elements to be installed. Do not secure the suspended duct or duct unit to trusses, ceilings, etc. building construction in places not provided for by the work production project.

Installation of air ducts from scaffolds, scaffolds and platforms must be carried out by at least two workers.

Alignment of flange holes when connecting air ducts should be done only with mandrels. Do not use your fingers to check the alignment of the holes of the flanges to be connected.

To prevent swaying or twisting of the lifted air duct blocks, hemp rope braces should be used.

Installation work on ventilation ducts may only be carried out with serviceable tools. Wrenches must exactly match the sizes of nuts and bolts, have no bevels on the edges and burrs on the handle. Do not unscrew or tighten the nuts with a wrench of large (compared to the head) size with a lining of metal plates between the edges of the nut and the wrench, as well as lengthen spanners by attaching another key or pipe.

Workplaces and work areas during installation in the dark should be illuminated. Illumination should be uniform, without the glare of lighting fixtures on workers. Work in unlit areas is not allowed.

Before starting work on the installation of internal systems, places that are dangerous for work and the passage of people should be fenced, provided with inscriptions and signs, safety signs should be installed, and when working at night, marked with light signals.

When installing the air ducts, it is necessary to provide for the installation of fasteners, for which the air duct installer can fix himself when working at height.

Operation of construction machines (lifting mechanisms, small-scale mechanization equipment), including Maintenance, should be carried out in accordance with the requirements of SNiP 12-03-2001 and the instructions of the manufacturers. The operation of lifting mechanisms, in addition, must be carried out taking into account PB 10-382-00 "Rules for the device and safe operation hoisting cranes ".

The places where electric welding works are performed with an open arc should be fenced with fireproof screens, shields, etc.

When electric welding works are performed in the open air, sheds made of non-combustible materials should be erected over the installations and welding stations. In the absence of sheds, electric welding work should be stopped during rain or snowfall.

To protect against drops of molten metal and slag falling during electric welding, a dense platform covered with sheets of roofing iron or asbestos cardboard must be installed under the welding place in places where people pass.

When installing ventilation ducts on roofs with a slope of more than 20 °, as well as regardless of the slope on wet and frosty or snow-covered roofs, workers must use safety belts, as well as ladders with a width of at least 0.3 m with transverse strips to support the legs; the ladders must be secured during operation.

Loading and unloading operations should be carried out in accordance with GOST 12.3.002-75 *, GOST 12.3.009-76 *.

Loading and unloading operations must be carried out in a mechanized way using lifting and transporting equipment and small-scale mechanization. It is necessary to lift loads manually in exceptional cases, observing the norms established by the current documents.

When loading and unloading ventilation air duct blanks and their parts, containers should be used. During lifting, lowering and moving of the container, workers should not be on it or inside it, as well as on adjacent containers.

Slinging and unfastening of goods should be carried out in accordance with PB 10-382-00.

The supply of materials, ventilation blanks, equipment to workplaces should be carried out in a technological sequence that ensures the safety of work. Workpieces and equipment should be stored at workplaces in such a way that they do not create a hazard during the work, the passages are not constrained, and it would be possible to assemble the air ducts into enlarged blocks. You need to follow correct placement equipment and workpieces on the floors, avoiding concentration and not exceeding the permissible loads per 1 m 2 of the floor.

Ventilation blanks should be stored in stacks no more than 2.5 m high on spacers and pads. Oversized and heavy equipment should be stored in one row on pads.

Storage area for billets and ventilation equipment on construction site must be fenced and located in the area of ​​an operating crane. The storage area should be planned, have slopes for water drainage, and in winter time it should be cleared of snow and ice.

Explosive or harmful paints and varnishes and other materials are allowed to be stored at workplaces in quantities not exceeding the replacement requirement. Such materials must be stored in tightly closed containers.

Between the stacks (racks) on sites and in warehouses, there should be at least 1 m wide passages and passages, the width of which depends on the dimensions of transport and handling facilities serving the warehouse or site.

The heads of the installation organizations are obliged to provide workers, engineering and technical workers and employees with overalls, footwear and other personal protective equipment in accordance with regulatory requirements.

All persons on the construction site are required to wear safety helmets. Workers and engineers without protective helmets and other necessary personal protective equipment are not allowed to perform work on the installation of air ducts.

When working at heights, ventilation installers must always wear safety belts.

Workers and employees receiving personal protective equipment (respirators, gas masks, safety belts, helmets, etc.) must be trained in how to use them.

All work on the installation of ventilation ducts should be carried out in the presence and under the guidance of responsible engineers in accordance with the rules for the production and acceptance of work in accordance with SP 73.13330. 2012 with strict adherence to labor safety requirements in accordance with:

P / p No.

Name of machines, mechanisms, machine tools, tools and materials

Brand

Unit rev.

Quantity

Paint spray gun with a productivity of 600 m 3 / h

SO-72

PCS.

Compressor with a capacity of 20 - 30 m 3 / h

SO-7A

Open end wrenches, double-sided

kit

Flat square, triangular, round, semicircular files with notches No. 1, 2, 3

Steel bench hammer

PCS.

Chisel

Fitting screwdriver (set)

kit

Combination pliers 3 E 1

Welder's shield

Mounting and traction mechanism

MTM-1.6

Rack jack

DR-3.2

Drilling machine

IE-1035

Grinder electric

Sh-178-1

Electric wrench

IE-3115B

Electric screwdriver

IE-3602-A

Electric puncher

IE-4712

Electric scissors

IE-5502

Assembly device for moving loads

PMPG-1

Manual winch

STD 999/1

Hydraulic jack

DGS-6.3

Blind riveting gun

STD 96/1

Safety steeplejack device

PVU-2

4 digits

Ventilation systems installer:

4 digits

3 ranks

2 discharges

As an example of the installation of ventilation ducts, we will take the installation of vertical air duct risers measuring 800 × 800 mm with an area of ​​100 m 2 using a hand winch.

Labor and machine time costs for the installation of ventilation ducts are calculated according to the "Uniform norms and prices for construction, installation and repair and construction work" (presented in table 7)

Measurement unit 100 m 2 ventilation ducts.

Table 14 - Calculation of labor costs and machine time

P / p No.

Justification (ENiR and other norms)

Name of technological processes

Unit rev.

Scope of work

Time rate

Labor costs

workers, man-hours

workers, man-hours

driver, man-h. (machine operation, machine-hour)

E9-1-46 No. 1a

Drilling holes with an electric drilling machine in building structures

100 holes

E1-2 Tab. 3 No. 1ab

Delivery of air duct parts to the installation site

100 t

0,0083

1,8 (1,8)

0,034

0,034 (0,034)

E10-5 Tab. 12 No. 4c

Assembly of air ducts into enlarged blocks, installation of fastening means, lifting and installation of blocks, connection installed unit with previously mounted, alignment and final fixing of the system

1 m 2

0,62

62,0

E10-13 Tab. 2d Will apply.

Installation of plugs on the upper ends of vertical air ducts

PCS.

0,59

0,59

TOTAL:

64,8

0,034 (0,034)

The duration of work on the installation of ventilation ducts is determined by the work schedule presented in the table.

Technical and economic indicators are.

Ministry of Education and Science of the Russian Federation

State educational institution

higher professional education

Samara State Architectural

university of construction

Department of Heat and Gas Supply and Ventilation

Technological maps of installation of ventilation and air conditioning systems

Methodical instructions

to course and diploma design

Approved by the Editorial and Publishing

university council

Samara 2011

UDC 697.912 (035.5)

Compiled by: Yu.I. Kasyanov, G.I. Titov, E.B. Filatova

Technological maps for the installation of ventilation and air conditioning systems: methodological instructions for course and diploma design. - Samarsk. state architect-builds un-t. - Samara, 2011 .-- 61 p.

These guidelines are for 5th-year and 6th-year students. distance learning directions "Heating, ventilation and air conditioning" specialty 27.01.09-65 "Heat and gas supply and ventilation" for the implementation of the course project on the discipline "Organization of construction production" and the same section of the diploma project.

Methodological guidelines have been developed in accordance with the educational and methodological complex of a higher school and include general rules for conducting installation work, the composition and procedure for developing technological maps, as well as standard technological maps for the main processes of installing ventilation and air conditioning systems.

These guidelines cannot be completely

or partially reproduced, duplicated (including photocopied)

and distributed without permission

Samara State University of Architecture and Civil Engineering.

Editor

Technical editor

Corrector

Signed to print

Format 6084. Offset paper. Operational printing.

Uch.-ed. l. CONV. print l. Circulation 100 copies. Order no.

Samara State University of Architecture and Civil Engineering.

443001 Samara, st. Molodogvardeyskaya, 194.

Printed in a typography

© Samara State

architectural and construction

university, 2011

Rules for conducting assembly and assembly work at the facility

The assembly production process can be divided into the following main stages:

    development of installation drawings, work production projects, flow charts;

    preparation of production in the assembly organization;

    execution of assembly units and parts at the procurement enterprise and the acquisition of the necessary materials and equipment;

    preparation of the construction object for the smooth and fast execution of installation work;

    installation and assembly works at the facilities;

    testing, adjustment and commissioning of mounted systems and devices.

Execution of works in such a sequence ensures the rhythm and economic efficiency of the assembly production. Preparation of production in the installation organization and preparation of the object itself for installation can and should be carried out in parallel and at the same time.

At present, the installation of systems at sites is carried out mainly from enlarged units coming from procurement enterprises. However, if the blanks are delivered to the objects in the form of separate elements, then the installation should begin with the assembly of these elements into enlarged units and blocks at the object itself. Modern equipment of installation organizations with truck cranes, hydraulic lifts, various drive and manual winches allows you to operate large assemblies.

Thus, there are four basic rules for organizing the installation of internal sanitary systems.

First rule - installation is carried out in three steps: pre-assembly, installation in the design position and connection of assembly joints, not counting the installation of fasteners by a specialized team.

Second rule - the order of performance of work must be carried out in a firm sequence, due to considerations of construction technology.

Third rule - installation of pipelines, air ducts and equipment should be carried out on pre-installed fastening means. Advance installation of brackets, hangers, clamps, etc. ensures that the slopes of the system elements provided for by the project are observed either strictly horizontally or vertically.

Fourth rule - maximum mechanization of all types of work. This leads to a reduction in the timing of assembly and assembly work and a decrease in their labor intensity.

Most of the assembly operations are done manually, so Special attention should be directed to the mechanization of auxiliary work. This group of works includes the delivery of blanks and equipment to the interior of the facility or to the sites to the places of their final placement. In this case, the production process of installation can be accelerated by the maximum combination of transport operations with the installation of equipment (especially heavy) in the design position, i.e. with rigging works. At the same time, it is necessary to strive for a comprehensive mechanization of operations using several sequentially working mechanisms (for example, vertical lifting - a truck crane, horizontal movement - trolleys or rollers in combination with winches, straightening - hoists or jacks).

To reduce labor costs for assembly work, small-scale mechanization tools should be widely used: electric nutrunners, drilling machines, etc. These tools and devices are included in kits for assembly teams.

In addition, it should be emphasized that when organizing and installing various systems, including ventilation and air conditioning systems, the safe performance of work must be ensured... This implies the device of good lighting of workplaces, the presence of fences, if the installation is carried out at a height, the use of serviceable tools, mechanisms, construction machines, which must correspond to the nature of the performed construction process, as well as the use of individual means of ensuring labor safety.


page 1



page 2



p. 3



page 4



p. 5



page 6



page 7



page 8



page 9



page 10



page 11



p. 12



p. 13



p. 14



p. 15



page 16



p. 17



p. 18



p. 19



page 20



p. 21



page 22



page 23



page 24



p. 25



p. 26



page 27



page 28



page 29



page 30

Typical flow chart for installation and
installation of internal ventilation systems and
air conditioning with supply and exhaust
installations and equipment systems
refrigeration

Typical technological map
(TTK)

Project code: 1012/40

Explanatory note

2012 r.

1. General data. 2

2. Organization and technology of the construction process. 2

2.1. Materials and manufacture of air ducts. 2

2.2. Preparatory work .. 4

2.2.1. General Provisions. 4

2.2.2. Delivery, warehousing and storage of elements of ventilation and air conditioning systems. 4

2.3. Works of the main period. Installation .. 8

2.3.1. Installation of internal ventilation and air conditioning systems. General Provisions. eight

2.3.2. Installation of air ducts. nine

2.3.3. Installation of fans. ten

2.3.4. Installation of equipment for refrigeration systems. eleven

2.4. Testing and commissioning ... 11

2.4.1. Testing and commissioning of internal ventilation and air conditioning systems. eleven

2.4.2. Testing of refrigeration systems. 12

3. Requirements for the quality and acceptance of works. 12

3.1. Requirements for the quality of work on the installation of air ducts. 13

3.2. Requirements for the quality of work on the installation of fans. 16

3.3. Requirements for the quality of work on the installation of air conditioners. eighteen

4. Safety requirements and labor protection, environmental and fire safety. eighteen

5. The need for material and technical resources. 22

6. Technical and economic indicators. 23

1. GENERAL DATA

This technological map is designed for the installation and installation of internal ventilation and air conditioning systems with air handling units and equipment for refrigeration systems in industrial, administrative, public and residential buildings.

The technological map was drawn up taking into account the requirements of the following regulatory documents:

Air ducts made of thin sheet roofing steel with a diameter and size of the larger side up to 2000 mm, should be made:

Spiral-lock or longitudinal seam on rebates;

Spiral welded or longitudinal welded.

Air ducts made of thin sheet roofing steel with a side size of more than 2000 mm should be made panel (welded, glue-welded).

Metal-plastic air ducts should be made on folds, and from stainless steel, titanium, as well as from sheet aluminum and its alloys - on folds or welded.

Air ducts made of sheet aluminum and its alloys with a thickness of up to 1.5 mm should be performed on folds, with a thickness of 1.5 to 2 mm - on folds or welding, and with a sheet thickness of more than 2 mm - on welding.

Longitudinal folds on air ducts made of thin sheet roofing and stainless steel and sheet aluminum with a diameter or size of the larger side of 500 mm or more must be fixed at the beginning and end of the duct link by spot welding, electric rivets, rivets or bulging.

Folds on air ducts with any metal thickness and manufacturing method must be cut-off.

The end sections of the seam seams at the ends of the air ducts and in the air distribution openings of the metal-plastic air ducts must be fixed with aluminum or steel rivets with an oxide coating, ensuring operation in aggressive environments specified in the working documentation.

Seam seams should have the same width along their entire length and be evenly and tightly upset.

In rebated air ducts, as well as in cutting plans, there should be no cross-shaped joints of seams.

On straight sections of rectangular air ducts with a side cross-section of more than 400 mm, it is necessary to constructively perform rigidity in the form of bends (ridge) with a step of 300 - 500 mm along the perimeter of the air duct or diagonal bends (ridge). If the side is more than 1000 mm and the length is more than 1000 mm, in addition, it is necessary to install external stiffening frames, with a step of no more than 1250 mm. Stiffening frames must be securely fixed by spot welding, rivets or self-tapping screws.

Stiffening frames should be installed on metal-plastic air ducts using aluminum or steel rivets with an oxide coating, ensuring operation in aggressive environments defined by the working documentation.

Elements of fittings should be connected to each other on zigzags, folds, welding, rivets.

Elements of fittings made of metal-plastic should be connected to each other on the folds.

Zig joints for systems transporting air of high humidity or with an admixture of explosive dust are not allowed.

The connection of the sections should be performed:

for round air ducts in a flangeless way (nipple / sleeve), shroud connection or on flanges;

for rectangular ducts: busbar (large / small) or on flanges. The connections must be strong and tight.

Fastening the tire to the air duct should be done with rivets with a diameter of 4 - 5 mm, self-tapping screws (in the absence of fibrous components in the moving medium), spot welding, bulging every 200 - 250 mm, but not less than four. The inner corners of the tire should be filled with sealant.

Fastening of flanges to air ducts should be carried out by flanging with a persistent ridge, by welding, spot welding, on rivets with a diameter of 4 - 5 mm or self-tapping screws (in the absence of fibrous components in the transported medium), placed every 200 - 250 mm, but not less than four.

Regulating devices (dampers, throttle valves, dampers, regulating elements of air distributors, etc.) must be easy to close and open, as well as be fixed in a given position.

Air ducts made of non-galvanized steel, their connecting fasteners (including the inner surfaces of the flanges) must be primed (painted) at the procurement company in accordance with the working documentation. The final painting of the outer surface of the air ducts is carried out by specialized construction organizations after their installation.

Ventilation blanks must be completed with parts for their connection and fastening means.

2.2. Preparatory work

2.2.1. General Provisions

Installation must be carried out by industrial methods from air duct assemblies and equipment supplied as a complete set of large blocks.

Installation of systems should be carried out when the facility is ready for construction (seizure) in the amount of:

For industrial buildings - the entire building with a volume of up to 5000 m 3 and a part of the building with a volume of more than 5000 m 3;

For residential and public buildings up to five floors - a separate building, one or more sections; over five floors - five floors of one or more sections.

Another scheme of installation organization is possible, depending on the adopted constructive scheme.

2.3.2. Installation of air ducts

The method of installation of air ducts should be selected depending on their position (horizontal, vertical), location relative to structures (near the wall, near columns, in the interfarm space, in the shaft, on the roof of the building) and the nature of the building (one- or multi-storey, industrial, public and etc.).

Flexible air ducts made of fiberglass SPL, metal fabric, aluminum foil, etc., should be used as fittings of complex geometric shapes, as well as for connecting ventilation equipment, air distributors, silencers and other devices located in false ceilings, chambers, etc. flexible ducts are not allowed as straight links.

In order to reduce aerodynamic drag, parts from flexible sleeves in the mounted position must have a minimum compression ratio.

Installation of metal air ducts should be carried out, as a rule, in enlarged blocks in the following sequence:

Marking of installation sites for fastening means for air ducts;

Installation of fastening means;

Coordination with the builders of the locations and methods of fastening the lifting equipment;

Delivery of air duct parts to the installation site;

Checking the completeness and quality of the delivered air duct parts;

Assembly of air duct parts into enlarged blocks;

Installation of the unit in the design position and fixing it;

Installation of plugs on the upper ends of vertical air ducts located at a height of up to 1.5 m from the floor.

The length of the block is determined by the dimensions of the section and the type of connection of the air ducts, the conditions of installation and the availability of lifting equipment.

The length of enlarged horizontal air duct units connected on flanges should not exceed 20 m.

Diagrams of the organization of the working area during the installation of air ducts are given in Fig. 9 - 10.

Rice. 9. Diagram of the organization of the working area during the installation of air ducts
along the outer wall of the building

1 - console with block; 2 - winch; 3 - auto-hydraulic elevator;
4 - traverse; 5 - guy line; 6 - block

Rice. 10. Diagram of the organization of the working area during the installation of horizontal
air ducts in the building

1 - winch; 2 - traverse; 3 - enlarged unit of the air duct; 4 - pendants

2.3.3. Fan installation

The fans must be installed in the following sequence:

Acceptance of ventilation chambers premises;

Delivery of the fan or its individual parts to the installation site;

Installation of lifting equipment;

Slinging the fan or individual parts;

Lifting and horizontal movement of the fan to the installation site;

Fan installation (fan assembly) on supporting structures (foundation, platform, brackets);

Checking the correct installation and assembly of the fan

Fastening the fan to supporting structures;

Checking the fan operation.

During the installation of fans, a step-by-step operational control should be carried out in accordance with the operational control cards.

2.3.4. Installation of equipment for refrigeration systems

Installation of equipment for refrigeration systems should be carried out in the following sequence:

Acceptance of premises or sites for equipment;

Delivery of the installation or its individual parts to the installation site;

Installation of lifting equipment;

Slinging of the installation or its individual parts;

Lifting and horizontal movement of equipment to the installation site;

Installation (assembly) of equipment on supporting structures (foundation, site);

Checking the correctness of installation and assembly of equipment;

Fixing the unit to supporting structures;

Commissioning works

Checking the operation of the equipment.

2.4. Testing and commissioning

Upon completion of the installation work, the contractors must carry out tests of the internal systems. Tests must be carried out before finishing work begins.

Commissioning works are performed after completion of construction and installation works, during the preparation and transfer of systems to operation. As a rule, they consist of individual tests and complex trials.

Comprehensive testing of ventilation and air conditioning systems of a building (structure, etc.) is carried out according to the program and schedule developed by the general contractor or on his behalf by the commissioning organization. The results of complex tests are documented in the form of an act.

2.4.1. Testing and commissioning of internal ventilation and air conditioning systems

The final stage of installation of ventilation and air conditioning systems is commissioning and commissioning of systems. Acceptance of works is carried out in the following sequence:

Survey of hidden works;

Individual testing of ventilation equipment (running in);

Delivery for pre-start tests and commissioning.

Air ducts and

ventilation equipment hidden in mines, suspended ceilings, etc. The results of the acceptance of works hidden by subsequent works, in accordance with the requirements of the design and regulatory documents are drawn up by certificates of inspection of hidden works.

Check the tightness of the air duct sections hidden by building structures using the aerodynamic test method (if the requirements are specified in the working project); based on the results of a leak test, draw up an inspection report for hidden works.

Individual tests of ventilation equipment (running-in) are carried out in order to check the operability of electric motors and the absence of mechanical defects in the rotating elements of the equipment. As a rule, running-in is performed after equipment installation with a connected air duct network. In cases of installing large-sized equipment in hard-to-reach places (roofs of buildings, basements, etc.), it is recommended to run in before the equipment is delivered to the installation site (at the production base or directly at the construction site).

When running-in equipment with an unconnected mains, it is prohibited to switch on without creating an artificial resistance (plug 3/4 of the inlet opening).

The ventilation equipment is run-in within 1 hour, or by checking the current values ​​of the motor operating in operation.

The discrepancy between the readings should not exceed 10% of the current values I n indicated on the engine.

In the absence of power supply ventilation units and air conditioning according to a permanent scheme, electricity connection according to a temporary scheme and a check of the serviceability of starting devices is carried out by the general contractor.

Based on the results of testing (running-in) ventilation equipment, an individual equipment test certificate is drawn up (Appendix E, SP 73.13330.2012).

When setting up ventilation and air conditioning systems for the design air flow, you should perform:

Check the compliance of the actual design of ventilation and air conditioning systems with the design documentation and the requirements of SP 73.13330.2012;

Testing of fans during their operation in the network, checking the compliance of the actual technical characteristics with the passport data, including: air flow and total pressure, rotation speed, power consumption, etc.;

Checking the uniformity of heating (cooling) of heat exchangers and checking the absence of moisture carryover through the drip catchers of the irrigation chambers or air coolers;

Determination of the flow rate and resistance of dust collecting devices;

Checking the operation of natural ventilation exhaust devices;

Testing and adjusting the ventilation network of systems in order to achieve design indicators for air consumption in air ducts, local suction, for air exchange in rooms and determination of air leaks or losses in systems.

Deviations of air flow rates from those provided for in the design documentation after adjustment and testing of ventilation and air conditioning systems are allowed:

Within ± 8% - in terms of the air flow passing through the air distribution and air intake devices of general ventilation and air conditioning installations, provided that the required backpressure (vacuum) of air in the room is ensured;

Up to +8% - according to the air flow rate removed through local suction and supplied through the spray nozzles.

For each ventilation and air conditioning system, a passport is issued in two copies (Appendix G, SP 73.13330.2012).

2.4.2. Refrigeration testing

Testing of water cooling systems should be carried out with the heat generators and expansion vessels turned off by the hydrostatic method with a pressure equal to 1.5 working pressure, but not less than 0.2 MPa (2 kgf / cm 2) at the lowest point of the system.

The system is recognized as having passed the test if, within 5 minutes of keeping it under test pressure:

The pressure drop will not exceed 0.02 MPa (0.2 kgf / cm 2);

There are no leaks in welds, pipes, threaded connections, fittings and equipment.

3. REQUIREMENTS FOR QUALITY AND ACCEPTANCE OF WORKS

Quality control of work on the installation of ventilation and air conditioning systems should be carried out by specialists or special services that are part of the construction organization or attracted from outside, equipped with technical means that ensure the necessary reliability and completeness of control.

Quality control of work is carried out at all stages of the technological chain, starting from the development of the project and ending with its implementation at the facility on the basis of PPR and flow charts. Quality control should include incoming control of working documentation, structures, products, materials and equipment, operational control of individual installation processes or production operations, and assessment of the conformity of the work performed.

During the incoming inspection of the working documentation, it is checked for its completeness and the sufficiency of the technical information contained in it for the production of work.

During the incoming inspection of products, materials and equipment, it is checked by external examination that they comply with the requirements of standards or other regulatory documents and working documentation, as well as the presence and content of passports, certificates and other accompanying documents.

3.1. Requirements for the quality of work on the installation of air ducts

Air ducts should be installed in accordance with design references and elevations. The connection of the air ducts to the technological equipment must be carried out after its installation.

Air ducts intended for transporting humidified air should be installed so that there are no longitudinal seams in the lower part of the air ducts.

Air duct sections where dew may fall out of the transported humid air should be laid with a slope of 0.01 - 0.015 towards the drainage devices.

The spacers between busbars or duct flanges must not protrude into the ductwork.

Gaskets should be made of the following materials: foam rubber, tape porous or monolithic rubber with a thickness of 4 - 5 mm, polymer mastic bundle (PMZh) - for air ducts through which air, dust or waste materials move with temperatures up to 343 K (70 ° C) ...

To seal flangeless air duct connections, use:

Sealing tape of the "Guerlain" type - for air ducts through which air moves with a temperature of up to 313 K (40 ° C);

Mastic such as "Buteprol", Silicone and other certified sealants - for circular air ducts with temperatures up to 343 K (70 ° C);

Heat-shrinkable cuffs, self-adhesive tapes - for circular air ducts with temperatures up to 333 K (60 ° C);

Other sealing materials specified in the working documentation.

The bolts in the flange connections must be tightened with all the bolt nuts on the same side of the flange. When installing bolts vertically, the nuts should generally be on the underside of the joint.

Fastening of air ducts should be carried out in accordance with the working documentation.

Fasteners of horizontal metal non-insulated air ducts (clamps, hangers, supports, etc.) on a bandage flangeless connection should be installed:

At a distance of no more than 4 m from one another with circular duct diameters or dimensions of the larger side of a rectangular duct less than 400 mm.

At a distance of no more than 3 m from one another - with diameters of a circular duct or dimensions of the larger side of a rectangular duct of 400 mm or more.

Fasteners of horizontal metal non-insulated air ducts on a flange, nipple (sleeve) connection should be installed at a distance of no more than 6 m from one another:

For circular cross-sections up to 2000 mm diameter,

For rectangular section on flanges, bus on flange connection of circular section with a diameter of up to 2000 mm or rectangular section with dimensions of its larger side up to 2000 mm inclusive.

The distances between the fasteners of insulated metal air ducts of any cross-sectional size, as well as non-insulated air ducts with a circular cross-section with a diameter of more than 2000 mm or a rectangular cross-section with a larger side of more than 2000 mm, should be assigned by working documentation.

The fastening of the nipple (coupling) should be carried out with rivets with a diameter of 4 - 5 mm or self-tapping screws with a diameter of 4 - 5 mm every 150 - 200 mm of a circle, but not less than three.

The clamps should fit tightly around the metal air ducts.

Mounts for vertical metal ducts should be installed at a distance of no more than 4.5 m from one another.

Fastening of vertical metal air ducts inside the premises of multi-storey buildings with a floor height of up to 4.5 m should be carried out in the interfloor ceilings.

Fastening of vertical metal air ducts indoors with a floor height of more than 4.5 m and on the roof of the building should be determined by the working documentation.

Fastening of guy wires and hangers directly to the duct flanges is not allowed. The tension of the adjustable hangers must be uniform.

The deviation of the ducts from the vertical should not exceed 2 mm per 1 m of the duct length.

Freely suspended air ducts should be braced by installing double hangers every two single hangers with a suspension length of 0.5 to 1.5 m.

For hangers longer than 1.5 m, double hangers should be installed through each single hanger.

Air ducts should be reinforced so that their weight is not transferred to the ventilation equipment.

Air ducts should generally be connected to fans through vibration-damping flexible inserts made of fiberglass or other material that provides flexibility, density and durability.

Anti-vibration flexible inserts should be installed immediately prior to individual testing.

When making straight sections of air ducts from a polymer film, bends of the air ducts are allowed no more than 15 °.

To pass through the enclosing structures, the air duct made of plastic film must have metal inserts.

Air ducts made of plastic film should be suspended on steel rings made of wire with a diameter of 3 - 4 mm, located at a distance of no more than 2 m from one another.

The diameter of the rings should be 10% larger than the diameter of the duct. Steel rings should be fastened with a wire or plate with a cutout to a supporting cable (wire) with a diameter of 4 - 5 mm, stretched along the axis of the duct and fixed to the building structures every 20 - 30 m.

To exclude longitudinal displacements of the air duct when it is filled with air, the polymer film should be stretched until the slack between the rings disappears.

Table 1. Map of operational control of the installation of metal air ducts

Technological process

Controlled indicators

Measuring tool

Control type

Delivery of air duct parts to the installation site

Checking the completeness of the ventilation system (availability of control devices, fasteners, etc.)

Permanent 100%. Visually. Compliance with the picking list, sketches

Marking of installation sites for fixing air ducts

Installation step of fasteners in accordance with SNiP 3.05.01-85

Roulette I= 10 m

Plumb line M = 200 g

Permanent 100%

Drilling depth

Steel meter

Permanent 100%

Installation of fasteners

Fastening strength

Permanent 100%.

Visually

Assembly into enlarged units of parts of air ducts, regulating and air distribution devices at the site

Correctness of assembly in accordance with the project. Tightness of connections

Visually.

Permanent 100%

Ascent to the design level and interconnection of enlarged units of air ducts with preliminary fastening

The position of transverse seams and detachable duct connections relative to building structures. Verticality of risers. Absence of kinks, curvature in straight sections of air ducts

Plumb line M= 200 g

Visually

Permanent 100%

Alignment of the mounted air ducts and their final fixing

The horizontal installation of the air ducts and the observance of the slopes in the distribution sections of the air ducts. Density of coverage of the duct with clamps. Reliability and appearance of fasteners

Metal meter, tape measure I= 10 m, level I= 300 mm

Permanent 100%.

Visually

Connection of air ducts to ventilation equipment

Correct installation of soft inserts (no slack)

Permanent 100%.

Visually

Testing the operation of regulating devices

Smooth operation of regulating devices

Output 100%.

Visually

3.2. Requirements for the quality of work on the installation of fans

Radial fans on vibration bases and on a rigid base, installed on foundations, must be fixed with anchor bolts.

When installing fans on spring vibration isolators, the latter must have a uniform settlement. Vibration isolators do not need to be fastened to the floor.

When installing fans on metal structures, vibration isolators should be attached to them. Elements of metal structures to which vibration isolators are attached must match the corresponding elements of the fan unit frame.

When installed on a rigid base, the fan frame must fit snugly against the sound insulating pads.

The gaps between the edge of the front disc of the impeller and the edge of the inlet pipe of the radial fan, both in the axial and in the radial direction, should not exceed 1% of the impeller diameter.

The shafts of the radial fans must be installed horizontally (the shafts of the roof fans - vertically), the vertical walls of the casings of the centrifugal fans must not be skewed or tilted.

The gaskets for the split fan shrouds should be of the same material as the gaskets for the ductwork of this system.

The motors must be precisely aligned with the installed fans and secured. The axes of the pulleys of electric motors and fans with a belt drive must be parallel, and the center lines of the pulleys must coincide. The belts must be tensioned according to the manufacturer's requirements.

The motor skids must be mutually parallel and level. The support surface of the slide must be in contact over the entire plane with the foundation.

Couplings and belt drives should be protected.

The fan suction opening, which is not connected to the air duct, must be protected with a metal mesh with a mesh size not exceeding 70 × 70 mm.

Table 2. Map of operational control of installation of centrifugal fans

Technological process

Controlled indicators

Measuring tool

Control type

Supply of the fan unit to the installation site

Checking the availability and quality of component parts

Permanent 100%.

Installation of the frame on the stands. Installation of vibration isolators under the frame

The horizontality of the foundation, frame

Level I= 300 mm

Permanent 100%

Installation of fans on a frame with vibration isolators

Pulley vertical, shaft horizontal

Plumb line M= 200 g

Permanent 100%

Assembly of fans on the frame: installation of the fan frame; installation of the lower part of the fan casing; installation of the turbine with fastening of its frame to the frame; installation of the inlet pipe

Fastening strength. Clearance between the edge of the front disc of the impeller and the edge of the inlet. Fastening strength

Visually.

Permanent 100%

Installation of the upper part of the casing and connection on the flanges of individual parts of the fan casing

Tightness of the connection

Visually.

Permanent 100%

Adjustment and final fastening of vibration isolators to the frame

Uniform settlement of vibration isolators. The strength of fastening vibration isolators to the frame

Visually.

Permanent 100%

Balancing the turbine before starting

Correct position of the turbine wheel

Permanent 100%.

(when scrolling, the risks should not match)

Installing the skid and the electric motor on the skid

Parallelism of the sled. The strength of the fastening of the electric motor to the slide. The strength of the connection between the electric motor and the fan. Parallelism of the axes of the fan and motor shafts. Ease of rotation of the shafts of the fan and electric motor

Level I= 300 mm

Permanent 100%. Visually

Visual, freehand testing

Installing a belt drive on pulleys. Belt drive guard

Coaxiality of grooves for V-belts of fan and motor pulleys. Correct belt tension

Cord (tension of the cord in the plane of the ends of the pulleys), steel meter, testing by hand

Permanent 100%

Connecting air ducts to the fan with the installation of flexible connectors

Tightness of connections. No slack in flexible joints

Visually.

Permanent 100%

Table 3. Map of operational control of installation of axial fans

Technological process

Controlled indicators

Measuring tool

Control type

Quality (no mechanical damage), completeness

Permanent 100%.

Visually, compliance with the passport data of the fan and electric motor

Installation of the fan unit on metal brackets. Fan mount

The strength of the supporting structures. Fastening strength of the fan to the supporting structures. Verticality, horizontal

Plumb line M= 200 g

Visually.

Permanent 100%

Checking fan operation

The gap between the ends of the blades and the shells. Correct direction and ease of rotation of the impeller

Permanent 100%.

Visual, freehand testing

Table 4. Map of operational control of installation of roof fans

Technological process

Controlled indicators

Measuring tool

Control type

Supply of a fan complete with an electric motor to the installation site

Completeness, quality (no mechanical damage)

Permanent 100%.

Visually, compliance with the passport data of the fan and electric motor

Checking the horizontal position of the cup support flange

Horizontality

Level I= 300 mm

Permanent 100%

Connecting the self-opening valve to the fan

Ease of valve movement

Permanent 100%.

Visual, freehand testing

Installation of the fan casing on the glass with its fastening with anchor bolts

Fastening strength of the fan to the supporting structures. The verticality of the shaft. Ease of rotation of the shafts of the fan and electric motor. Clearance between inlet and impeller

Plumb line M= 200 g

Permanent 100%.

Visual Freehand Testing

Permanent 100%

Checking fan operation

Correct direction of rotation of the wheel

Permanent 100%.

Visually (in accordance with the project)

3.3. Requirements for the quality of work on the installation of air conditioners

Air heaters of air conditioners should be assembled on gaskets made of certified material, with a heat resistance corresponding to the temperature of the heating medium. The rest of the blocks, chambers and units of air conditioners should be assembled on gaskets made of tape rubber 3-4 mm thick, supplied with the equipment.

Air conditioners must be installed horizontally. The walls of chambers and blocks should not have dents, distortions and slopes.

The valve blades should turn freely (by hand). In the "Closed" position, a tight fit of the blades to the stops and to each other must be ensured.

Supports of chambers and air conditioner units must be installed vertically.

Flexible air ducts should be used in accordance with the working documentation as fittings of complex geometric shapes, as well as for connecting ventilation equipment, air diffusers, silencers and other devices located in suspended ceilings and chambers.

The use of flexible air ducts as main air ducts is not allowed.

Fastening of fan coil units, door closers, split systems should be carried out in accordance with the recommendations of the manufacturers.

4. REQUIREMENTS FOR SAFETY AND LABOR PROTECTION, ENVIRONMENTAL AND FIRE SAFETY

The installation of ventilation ducts must be carried out in accordance with the requirements of safety, sanitation and occupational health, established by building codes and rules for occupational safety in construction.

Before being admitted to work on the installation of ventilation ducts, the heads of organizations are required to provide training and briefing on occupational safety at the workplace.

Persons at least 18 years of age who have undergone a medical examination without contraindications to work at height, have professional skills, have been trained in safe methods and techniques of work and have received an appropriate certificate are allowed to work at heights.

Individuals (workers and engineers and technicians) at least 18 years of age who have passed a medical examination and recognized as fit for performance of climbing work, having experience of climbing work for at least one year and a wage category not lower than the third.

Workers admitted to climbing work for the first time must work for one year under the direct supervision of experienced workers appointed by order of the organization.

Electric welding works are allowed to persons who have undergone appropriate training, instruction and testing of knowledge of the rules of safe work with registration in a special magazine and having a qualification certificate. Persons with medical contraindications are not allowed to work on electric welding at a height.

Persons at least 18 years of age who have passed a medical examination, trained in the rules of using the tool, labor safety and have an electrical safety group of at least II, and for connecting and disconnecting electric outlets with a group of at least III are allowed to work with an electrified tool. All electrified tools are subject to registration and registration in a special journal. Each copy of the instrument must have a reference number. Monitoring the serviceability and timely repair of electrified tools is assigned to the department of the chief mechanic of the construction organization. Before issuing an electrified tool, it is necessary to check its serviceability (no short circuit to the body, insulation at the supply wires and handles, the condition of the working part of the tool) and its operation at idle speed.

Responsibility for the correct organization of the safe conduct of work at the facility rests with the contractor and the foreman.

The admission of unauthorized persons, as well as drunken workers to the territory of the construction site, to production, sanitary premises and workplaces is prohibited.

Work on the installation of ventilation and air conditioning systems, as well as equipment for refrigeration systems are carried out according to the permit for work in conditions of hazardous and (or) harmful production factors.

Installation should be carried out only if there is a work production project, flow charts or wiring diagrams. In the absence of these documents, installation work is prohibited.

The procedure for performing the installation, determined by the project for the production of work, must be such that the previous operation completely excludes the possibility of industrial hazards when performing subsequent ones. Installation of air ducts and equipment parts for ventilation, air conditioning and refrigeration systems should, as a rule, be carried out in large blocks using lifting mechanisms.

No people should be under the elements to be installed. A suspended air duct or a block of air ducts must not be secured to trusses, ceilings and other building structures in places not provided for by the work production project.

Installation of air ducts from scaffolds, scaffolds and platforms must be carried out by at least two workers.

Alignment of flange holes when connecting air ducts should be done only with mandrels. Do not use your fingers to check the alignment of the holes of the flanges to be connected.

To prevent swaying or twisting of the lifted air duct blocks, hemp rope braces should be used.

Installation work on ventilation ducts may only be carried out with serviceable tools. Wrenches must exactly match the sizes of nuts and bolts, have no bevels on the edges and burrs on the handle. Do not unscrew or tighten the nuts with a wrench of large (compared to the head) sizes with a lining of metal plates between the faces of the nut and the wrench, and also lengthen the wrenches by attaching another wrench or pipe.

Workplaces and work areas during installation in the dark should be illuminated. Illumination should be uniform, without the glare of lighting fixtures on workers. Work in unlit areas is not allowed.

Before starting work on the installation of internal systems, places that are dangerous for work and the passage of people should be fenced, provided with inscriptions and signs, safety signs should be installed, and when working at night, marked with light signals.

When installing the air ducts, it is necessary to provide for the installation of fasteners, for which the air duct installer can fix himself when working at height.

The operation of construction machines (lifting mechanisms, small-scale mechanization), including maintenance, must be carried out in accordance with the requirements of SNiP 12-03-2001 and the instructions of the manufacturers. The operation of lifting mechanisms, in addition, must be carried out taking into account PB 10-382-00 "Rules for the construction and safe operation of lifting cranes".

The places where electric welding works are performed with an open arc should be fenced with fireproof screens, shields, etc.

When electric welding works are performed in the open air, sheds made of non-combustible materials should be erected over the installations and welding stations. In the absence of sheds, electric welding work should be stopped during rain or snowfall.

To protect against drops of molten metal and slag falling during electric welding, a dense platform covered with sheets of roofing iron or asbestos cardboard must be installed under the welding place in places where people pass.

When installing ventilation ducts on roofs with a slope of more than 20 °, as well as regardless of the slope on wet and frosty or snow-covered roofs, workers must use safety belts, as well as ladders with a width of at least 0.3 m with transverse strips to support the legs; the ladders must be secured during operation.

Loading and unloading operations should be carried out in accordance with GOST 12.3.002-75 *, GOST 12.3.009-76 *.

Loading and unloading operations must be carried out in a mechanized way using lifting and transporting equipment and small-scale mechanization. It is necessary to lift loads manually in exceptional cases, observing the norms established by the current documents.

When loading and unloading ventilation air duct blanks and their parts, containers should be used. During lifting, lowering and moving of the container, workers should not be on it or inside it, as well as on adjacent containers.

Slinging and unfastening of goods should be carried out in accordance with PB 10-382-00.

The supply of materials, ventilation blanks, equipment to workplaces should be carried out in a technological sequence that ensures the safety of work. Workpieces and equipment should be stored at workplaces in such a way that they do not create a hazard during the work, the passages are not constrained, and it would be possible to assemble the air ducts into enlarged blocks. It is necessary to monitor the correct placement of equipment and workpieces on the floors, avoiding concentration and not exceeding the permissible loads per 1 m 2 of the floor.

Ventilation blanks should be stored in stacks no more than 2.5 m high on spacers and pads. Oversized and heavy equipment should be stored in one row on pads.

The storage area for billets and ventilation equipment at the construction site must be fenced and located in the area of ​​an operating crane. The storage area should be planned, have slopes for water drainage, and in winter time it should be cleared of snow and ice.

Explosive or harmful paints and varnishes and other materials are allowed to be stored at workplaces in quantities not exceeding the replacement requirement. Such materials must be stored in tightly closed containers.

Between the stacks (racks) on sites and in warehouses, there should be at least 1 m wide passages and passages, the width of which depends on the dimensions of transport and handling facilities serving the warehouse or site.

The heads of the installation organizations are obliged to provide workers, engineering and technical workers and employees with overalls, footwear and other personal protective equipment in accordance with regulatory requirements.

All persons on the construction site are required to wear safety helmets. Workers and engineers without protective helmets and other necessary personal protective equipment are not allowed to perform work on the installation of air ducts.

When working at heights, ventilation installers must always wear safety belts.

Workers and employees receiving personal protective equipment (respirators, gas masks, safety belts, helmets, etc.) must be trained in how to use them.

All work on the installation of ventilation ducts should be carried out in the presence and under the guidance of responsible engineers in accordance with the rules for the production and acceptance of work in accordance with SP 73.13330. 2012 with strict adherence to labor safety requirements in accordance with:

Flat square, triangular, round, semicircular files with notches No. 1, 2, 3

Steel bench hammer

Welder's shield

Mounting and traction mechanism

Rack jack

Drilling machine

Electric grinder

Electric wrench

Electric screwdriver

Electric puncher

Electric scissors

Assembly device for moving loads

Manual winch

Hydraulic jack

Blind riveting gun

Safety steeplejack device

6. TECHNICAL AND ECONOMIC INDICATORS

Technical and economic indicators are calculated for the installation of air ducts.

The composition of the complex team for the installation of air ducts, taking into account the possibility of combining professions, is shown in Table 6.

Table 6 - Composition of the brigade

As an example of the installation of ventilation ducts, we will take the installation of vertical air duct risers measuring 800 × 800 mm with an area of ​​100 m 2 using a hand winch.

Labor and machine time costs for the installation of ventilation ducts are calculated according to the "Uniform norms and prices for construction, installation and repair and construction work" (presented in table 7)

Measurement unit 100 m 2 ventilation ducts.

Table 14 - Calculation of labor costs and machine time

Justification (ENiR and other norms)

Scope of work

Time rate

Labor costs

workers, man-hours

workers, man-hours

driver, man-h. (machine operation, machine-hour)

E9-1-46 No. 1a

Drilling holes with an electric drilling machine in building structures

E1-2 Tab. 3 No. 1ab

Delivery of air duct parts to the installation site

E10-5 Tab. 12 No. 4c

Assembly of air ducts into enlarged blocks, installation of fastening means, lifting and installation of blocks, connection of an installed block with a previously mounted one, alignment and final fastening of the system

E10-13 Tab. 2d Will apply.

Installation of plugs on the upper ends of vertical air ducts

The duration of work on the installation of ventilation ducts is determined by the work schedule presented in Table 8.

Technical and economic indicators are:


Table 8 - Calendar plan production of works

Name of technological processes

Scope of work

Labor costs

The accepted composition of the link

Process duration, h

Work shifts

workers, man-hours

driver, man-hours, (work of machines, machine-hours)

Working hours

Drilling holes in building structures

Ventilation systems installer

Delivery of air duct parts to the installation site

Loader driver

rigger

Assembly of air ducts into enlarged blocks, lifting and installation of blocks, alignment and final fixing of the system

Ventilation system installers

Installation of plugs on the upper ends of vertical air ducts

Ventilation system installers

A typical flow chart for the installation of ventilation is drawn up for forced ventilation systems that include a network of air ducts. Its main purpose is to familiarize workers and engineers with how work should be done to install ventilation ducts, help in the location of equipment inside the room, the correct distribution of technological processes that will subsequently take place in production, etc.

How to install ventilation ducts correctly

Most of the work in the installation of air conditioning and ventilation systems is occupied by the installation of ventilation ducts.

Industrial ventilation

And this is not strange, because they are located inside the entire building, if the premises are used for industrial purposes, then it is also large, plus they often have to be installed at a high height, and this greatly complicates the matter. As a result, it is necessary to resort to the help of special machines and equipment. Most often these are self-propelled cranes, mobile assembly platforms, hydraulic lifts, and more.

The complexity of installation is influenced by a lot of factors:

  • Complexity of the designed system;
  • Features of the building structure;
  • Ambient conditions, etc.

To simplify technological process air duct installations, assemblies are made in advance, consisting of straight sections of ventilation pipes and fittings. After installing each node, you need to check with the data contained in the flow chart for the installation of ventilation.

Stages of installation of horizontal metal ventilation ducts

In order to qualitatively establish a network of ventilation ducts, you need to adhere to a certain algorithm of actions.

Fastening

The fastening means are installed first. This is done by welding them to embedded parts or using a special assembly gun... Places are outlined where lifting mechanisms will be located, scaffolding, towers and so on are being prepared. On inventory stands small parts assembled into knots, knots from ventilation ducts are made on the floor big size... Clamps and other fasteners are installed.

When the intermediate preparation is over, the knots are traced, at the ends of the knots, guys from the rope are tied.

The preparatory work is over, the installation can begin. With the help of special lifting mechanisms, the nodes are brought to the previously marked places and suspended from the mountings. It remains, using a flange, to attach a part of the system to the previously mounted unit.

There are other options for installing air ducts. The method is selected depending on their position in space, the characteristics of the industrial facility, the surrounding conditions, the location of the air ducts (inside or outside the building) and others.

If the ventilation system includes air conditioning and air heating, then it should be designed in accordance with all clauses of SNiP 2.04.05-91, while providing in advance for the possibility of breakdown and repair, and regulatory requirements.

Basic installation positions

It is important to correctly position the ventilation ducts in relation to the building structures. For this, special recommendations have been developed to properly secure round and rectangular air ducts. Basic guidelines and sizes are given below.

The axes of the ventilation pipes are placed parallel to the planes next to which they are mounted. It is necessary to choose the correct distance (taken in millimeters) from the plane of the wall (ceiling, floor) to the pipe axis. If channels with a circular cross-section are used: L = 0.51Dmax + 50, where Dmax is largest diameter duct including insulator.

Ventilation ducts

In the case of using channels with a rectangular cross-section, the formula looks like this: L = 0.5bmax + x, where bmax is the maximum channel width; x is the distance between outer surface pipes and a wall, should be at least 5 cm.

It is accepted that for pipes with a width of 10 to 40 cm x = 10 cm, 40 ... 80 cm x = 20 cm, 80 ... 150 cm x = 40 cm. The distance from the channel axis to the electric wire is also important. Round section air ducts: L = 0.5Dmax + 300. With a rectangular section: L = 0.5bmax + 300.

If two ventilation branches pass in parallel, then the following minimum distance between their axes is adhered to. Round section: L = 0.5 (Dmax + D'max) +250. Rectangular section: L = 0.5 (bmax + b'max) + x.

In the case when ventilation pipes are mounted under the ceiling, the minimum distance to it must also be observed. Round section: L = 0.5Dmax + 100. Rectangular: L = 0.5bmax + x. If the air ducts pass through building structures, then a distance of 10 centimeters should be observed.

Connection of air ducts to each other

The network of ventilation ducts consists of separate small parts, which are interconnected by means of bands, slats, strips, bell-shaped and other connections.

Air line details

For the correct fastening of the ventilation pipes, use the working documentation and the relevant requirements. If flangeless connections are used in the fastening process, then the following distances between them are adhered to:

  • When using pipes with a diameter of less than 400 mm, the distance should be no more than 4 meters;
  • If the diameter is 400 mm or more, then the distance becomes up to 3 meters.

When installing air ducts in a horizontal position with a circular cross-section, the diameter of which is up to 2000 mm or rectangular with a side up to 2000 mm, the distance between the fasteners is assumed to be no more than 6 meters.

If the pipes are installed in a vertical position, the distance between the fixtures is up to 4 meters.

Installation design

Before installing the ventilation line, you need to correctly make the installation design. It consists of several main stages.

Axonometric diagram

At the first stage, an axonometric diagram of the system is drawn, then the network of air channels is divided into separate parts. Next, you should choose a way to connect small components with each other and with larger nodes. The places where the fasteners will be located in the future are determined. Also, sketches of non-standard parts are made, where all the necessary dimensions for their manufacture are indicated. And at the end, documents are drawn up for the installation design:

  • Drawings of non-standard parts;
  • Axonometric diagram;
  • Picking lists.

Depending on the region where the installation takes place ventilation system the kit will also depend required documents... But the three listed above will always be present.

Installation of air ducts in an industrial facility

STANDARD TECHNOLOGICAL CARDS FOR PRODUCTION OF SEPARATE TYPES OF WORK

STANDARD TECHNOLOGICAL MAP

FOR INSTALLATION OF BUILDING STRUCTURES

6307030131
41131

MOUNTINGCONSTRUCTIONS LARGE-PANEL RESIDENTIAL 9-FLOOR NOGO HOUSE SERIES 90

10. INSTALLATION OF VENTILATION UNITS OF TYPICAL FLOOR

MOSCOW 1991

1 AREA OF USE

1.1. A typical technological map was developed for the installation of ventilation blocks of a typical floor, a large-panel 9-storey residential building of series 90.

1.2. The scope of work considered in the map includes the installation of ventilation units.

1.3. All work on the installation of ventilation units is performed in three shifts. The card provides for the installation of ventilation units tower crane KB-405.1A with a carrying capacity of 10 tons at a building height of up to 30 m.

1.4. When linking a typical technological map to a specific object and construction conditions, the procedure for performing work on the installation of ventilation blocks, the placement of machines and equipment, the scope of work, and mechanization means, adopted in the map, is specified in accordance with design decisions.

2. ORGANIZATION AND TECHNOLOGY OF WORK PERFORMANCE

2.1. Prior to the installation of ventilation units, organizational and preparatory measures must be performed in accordance with SNiP 3.01.01-85 "Organization of construction production".

In addition, the following work must be performed:

mounted, external and internal wall panels (in the case of installation, ventilation units adjacent to internal wall panels and sanitary cabins);

all structures of a typical floor have been assembled, including floor slabs (in the case of installation of free-standing ventilation units);

cleared downstream channels ventilation unit from the remains of the solution and other foreign objects;

mechanisms, inventory and accessories were delivered to the site and prepared for work;

workers and engineers are familiar with the technology of work and trained in safe working methods.

2.2. It is recommended to install the aboveground part of the building, including ventilation blocks, with tower cranes.

The location of the tower crane and the distance of the crane runways from the building are set when linking the map, depending on the space-planning solution of the building and the brand of the crane. The maximum distance from the axis of movement of the crane to the wall is determined by its technical characteristics, the minimum - by the safety conditions of work in accordance with SNiP III-4-80 * "Safety in construction". The layout of the assembly valve is shown on,.

2.3. Transportation of ventilation units is carried out by semi-trailers-panel transporters in a vertical or slightly inclined (no more than 12 ° to the vertical) position.

Ventilation blocks are placed on panel carriers in accordance with the loading cards, which are drawn up at the manufacturing plants according to the installation schedule of objects.

The motor transport must have the necessary devices to ensure the stable position of the ventilation units during transportation and to protect them. them from damage.

Soft spacers should be placed under the cables securing the ventilation units to avoid damaging the edges and surfaces.

Installation of ventilation units is carried out mainly from vehicles. In the case when installation from vehicles is not possible, the ventilation units are unloaded onto a flashing located in the area of ​​operation of the assembly crane.

Store ventilation units in a warehouse should be in cassettes or in pyramids ().

and the unloading must be uniform on both sides of the pyramid to avoid overturning. Slinging and unbundling of ventilation blocks stored in a warehouse - a pyramid, is produced from its upper platform.

Loading and unloading operations and transportation ventilation blocks are produced in compliance with measures to exclude the possibility of damage.

The solution is prepared centrally and delivered to the object using road transport funds: auto locomotives, concrete trucks, concrete mixer trucks and dump trucks.

Mortar mixtures at the construction site should be stored in boxes - containers, in rotary buckets, in bunkers, in units and installations for receiving, mixing and dispensing mixtures.

Delivery of the solution to the place of work carry out assembly tap in mortar boxes.

2.4. Installation of ventilation units adjacent to internal wall panels and sanitary cabins is performed during the installation of internal wall panels, partitions and sanitary cabins. Installation of freestanding ventilation blocks produced after the installation of floor slabs.

Slinging ventilation blocks carry outuniversal traversefour-branch for two loops (). The angle of inclination of the lines to the vertical is allowed no more than 15 °.

The installation of ventilation blocks is carried out according to the grips (one block is taken as a seizure - a section) and is carried out in a certain technologicalsequences... Scheme sequences installation of ventilation units on the example of block - section 90-05 is shown on.

Ventilation blocks are installed on a layer cement mortar with alignment of channels in height and careful monolithing horizontal seams. To prevent ingress of solution into channels ventilation block, it is spread over the top of the template - frames with caps. After laying the mortar, the frame is removed and the installation is started ventilation block.

Installation of ventilation units adjacent to internal wall panels and sanitary cabins is carried out as follows:

the ventilation block supplied by a crane to a height of 0.2 - 0.3 m from the mortar bed is accepted by installers;

reconcile its position and lower it onto the mortar bed. At the same time, the installers make sure that the hinges of the lower-level unit enter the grooves of the unit to be installed. The alignment of the ventilation units is performed by aligning the axes of the two mutually perpendicular faces of the installed units at the level of the lower section with the risks of the axes of the lower unit. The blocks are installed relative to the vertical plane by verifying the planes of two mutually perpendicular faces using a plumb rail.

the adjusted ventilation unit is temporarily fixed to the inner wall panel with two clamps ();

after aligning and temporarily fixing the ventilation unit, the installers un-sling the unit.

Temporary fasteners (clamps) can be removed only after installing plumbing cabins adjacent to the installed blocks.

Installation of free-standing ventilation units is carried out in the following technological order:

the ventilation unit supplied to the installation site is received and directed into the hole in the floor slab. The installer, located on the underlying overlap, takes it at a distance of 0.2 - 0.3 m from the mortar bed and turns it in the desired direction;

the ventilation unit is lowered onto the prepared mortar bed and its position is adjusted, aligning the axes of the two mutually perpendicular faces of the unit at the level of the lower section with the risks of the axes of the lower unit. If there are deviations from the design position, the installers correct the bottom of the block with mounting crowbars;

installers located on the overlying floor adjust the position of the top of the block, and after reaching the design position, fixing it with wooden wedges ();

after the final alignment, making sure of the reliability of the temporary fastening, the block is unstopped.

The internal cavity of the channels must be cleaned from the squeezed out solution using a mop.

Places of passage of the ventilation unit through the floor slab are sealed with cement mortar.

2.6. When carrying out work in the winter, it is necessary to be guided by the instructions of SNiP 3.03.01-87 "Bearing and Fencing Structures", as well as the current instructions, manuals and special instructions of the project.

Winter working conditions determine the average daily outdoor temperature below 5 ° С and the minimum daily temperature below 0 ° С (SNiP 3.03.01-87).

In winter, it is necessary to ensure the correct storage and storage of the structure in the on-site warehouse, protecting them from the formation of ice. The top of the ventilation blocks in the warehouse is sewn with sheets of roll material.

Before lifting the ventilation unit, check whether it is frozen to the ground or neighboring products.

Preparation of ventilation units for installation includes cleaning them from snow and ice, especially carefully at the joints. Cleaning should be done with scrapers or steel brushes. At the end of the removal of ice, the abutting surfaces should be dried with a jet of hot air.

It is not allowed to use for cleaning the abutting surfaces of pairs, hot water or sodium chloride solution.

Before installing the ventilation units, remove snow and ice from the floor and butt joints, sprinkle with sand workplace, storage areas and aisles, flights of stairs and platforms, clear the channels of the mounted ventilation unit from snow.

Installation work in winter conditions should be carried out using the same tools, fixtures and fittings as in the summer.

All rigging and assembly devices must be kept free of ice and dried. Couplings and screw connections must be lubricated with oil.

Installation of ventilation units in winter conditions can be carried out with mortars with antifreeze additives, ensuring their hardening in the cold.

As antifreeze additives introduced into solutions, sodium nitrite ( NaNO 2 ), complex additive NKM (sodium nitrite + urea), potash ( K 2 CO 3 ) and a combined additive of potash and sodium nitrite.

The use of antifreeze additives - sodium nitrite, is recommended at ambient temperatures up to minus 15 ° С, NKM - up to minus 20 ° С, potash and a mixture of sodium nitrite with potash - up to minus 30 ° С.

The amount of anti-frost additives, depending on the outside air temperature, should be assigned in accordance with the "Manual for the installation of large-panel residential buildings with a small step", TsNIIEPzhilishcha, 1980.

When installing at temperatures below minus 20 ° C, the solution should be used one grade higher than the design grade.

The mortar for the next mounted ventilation unit should be spread immediately before its installation in place.

The use of a solution frozen and warmed with hot water is not allowed.

At the construction site, the usual mortar mixture must be stored in an insulated container located in a specially designated place, protected from wind and atmospheric precipitation.

Storage of a solution with the addition of sodium nitrite at temperatures up to minus 15 ° С, with potash - up to minus 30 ° С is allowed in an uninsulated container.

The work log should record the temperature of the outside air, the amount of additive introduced into the solution and other data reflecting the effect on the hardening process of the solutions.

Table 1

Name of a set of machines and equipment

Variant (facet code)

Technical specifications

Quantity, pcs.

Assembly crane

Tower crane with lifting capacity

Tower crane with lifting capacity of 9 t

Vehicles

Semi-trailer panel carrier of cassette type with a lifting capacity of 12 t

Semi-trailer panel carrier of the backbone type with a lifting capacity of 14t

Equipment

Compressor installation mobile

1 - ventilation blocks; 2 - pyramid warehouse.

Rice. - 3

Slinging diagram of the ventilation unit

1 - universal traverse (four-branch self-balancing)

Rice. - 4.

Scheme of assembly sequence of prefabricated structures of a typical floor at the reception of sections 90-05

Rice. - 5.

Note: 1. On the sequence diagram of the installation of structures, the numerator indicates the brand, and the denominator indicates the ordinal number of the installation of structures.

2. Structures marked with (*) are unloaded to an on-site warehouse and assembled in order of priority.

Alignment of the ventilation unit.

Scheme of temporary fastening of the ventilation unit to the wall panel.

Solution supply

Mortar shovel

Leveling mortar

TU 22-4629-80

Cleaning surfaces

Galvanized bucket

GOST 20558-82

Storage of water or solution in the workplace

Darning

266.000.000 trust "Mosorgstroy"

Sealing horizontal joints

Template frame with stubs

Mortar bed device

Mop

R.ch. MS-397 Institute "Ortyugstroy" of the Ministry of State Construction of the RSFSR

Cleaning ventilation ducts from solution

Measuring tape, metal

Measuring elements and staking out axes

Folding steel meter

TU 2-17-303-84

Measuring elements

Measuring ruler, metal

Plumb rail

3295.03.000 TsNIIOMTP Gosstroy of the USSR

Determination of verticality when installing blocks

Fitters booth

3295.07.000 TsNIIOMTP Gosstroy USSR

Winter heating room and tool storage

Construction helmet

Head protection

Safety belt

GOST 12.4.089-86

Fall protection

Gloves (mittens) special

Protection of hands from injury

The need for materials and semi-finished products for performing work on the installation of ventilation units on a typical floor is given in table. 6

Table 6

Name of material, design (brand, GOST)

Variant (facet code)

Initial data

Need

unit

amount of work in standard units

accepted material consumption rate

in materials

Cement mortar M100 (mortar bed) GOST 28013-89

100 pieces. blocks

Cement mortar M100 (for sealing the places where ventilation blocks pass through the floor slab) GOST 28013-89

7.8. Work areas, workplaces, driveways and approaches to them in the dark should be illuminated.

7.9. When carrying out installation work, use the system of conventional signals established by the administration. All signals are given only by one person (foreman, team leader, rigger), except for the “Stop” signal, which is given by any person who has noticed a clear danger (SNiP III-4-80 * p. 12.18).

7.10. On the site (seizure) where installation work is being carried out, it is not allowed to perform other work and find unauthorized persons (SNiP III-4-80 * p. 12.1).

7.11. The ventilation units should be installed in the technological sequence provided by the card.

In this case, the following installation rules must be observed:

before lifting the blocks, check the quality and reliability of their slinging;

it is not allowed to lift with a crane blocks that are clamped by other elements or frozen to the ground;

move blocks horizontally at a height of at least 0.5 m and at a distance of at least 1 m from other structures;

do not carry the ventilation units with a crane above the work place of installers, as well as over the seizure where other construction work is being carried out;

accept the supplied unit only when it is 0.2 - 0.3 m from the installation site. By accepting the item, assemblers do not should be between it and another structure.

7.12. Set ventilation blocks follow without jolts, avoiding blows to other structures.

7.13. During breaks in work, it is not allowed to leave lifted ventilation units or loads suspended.

7.14. Installed in the design position, the ventilation blocks must be fixed so that their stability is ensured and geometric immutability.

Unslinging of structures installed in the design position is allowed to be performed after their permanent or temporary reliable fastening. It is not allowed to move the installed structures after they have been unfastened.

7.15. The mortar boxes should only be installed in junctions floor slabs to each other, i.e. e. over the interior wall panels.

7.16. When preparing a mortar mixture using chemical additives, it is necessary to take measures to prevent skin burns

and damage to the eyes. This work should be carried out in accordance with the "guidelines for the use of concrete with antifreeze additives ".

7.17. When carrying out work in the winter, staircases, flights, walkways, mounted ventilation blocks, as well as mounting devices must be cleaned of snow and ice, and the workersplacesto sprinklesand.

7.18. Notallowedfulfillassemblyworkonheight inopenlocationsatspeedthe wind 15 m/ withandmore, atice, thunderstormandfog, excludingvisibilityvwithinfrontworks.

7.19. Ifvprocessmountingvent blocksformedopenopenings, Towhichavailableaccess, of people, necessarysetinventoryportablefencesorenjoyshields foroverlapholes.

7.20. Atworkonheightinstallersandotherworkersmustto beequipped withverifiedandWage workers-assemblers r.-k.

20 - 56

Wages of machine operators, r.-k.

7 - 10

Duration of work, shifts

0,99

Production of ventilation units per worker per shift

6,99

Conditional costs for mechanization, rubles - to.

31 - 30

The amount of variable costs, rubles - to.

51 - 86

9. FACETED FACTOR CLASSIFIER

FACET 01

Unloading elements for on-site salary

Factor name

Justification

Factor value

Weight unloaded ventilation blocks, t, up to: 1

§ E 1-7, No. 28 a, b K = 0.8 (PR-2)

By calculation

2

Too, 29 a, b

N.vr. and the prices for the driver multiplied by 0.688. N.vr. and the prices for the rigger multiplied by 0.692

3

The same, No. 30 a, b

N.vr. and the prices for the driver multiply by 0.438. N.vr. and the prices for the rigger multiplied by 0.431

FACE 0 2

Height from the level of planning marks

Factor name

Justification

Factor value

Rygot, m, up to: 15

ENiR, Sat. 4, no. 1, introduction, clause 3

By calculation

Too, HF-1

Time rate and rate multiply by 1.05

FACET 03

Weightmountedelement

Factor name

Justification

Factor value

Ventilation unit weight, t, up to:

§ E 4-1-14, * 1

By calculation

The same, no. 2

Time rate and rate multiplied by 1.5

The same, no. 3

The same, no. 4

and

FACE 04

InningssolutionToplaceworktowercrane(heightliftingbefore 12 m)

FACET 05

The height of the solution lifting to the place of work with a tower crane

Factor name

Justification

Factor value

Lifting height, m, up to:

§ E 1-7, No. 9 a, b

By calculation

The same, No. 9a, b + c, d

Time rate and rate multiply by 1.2037

Too, 9a, b + 2 c, d

The same, 1.407

The same, No. 9 a, b + 3 c, d

The same, 1.611

The same, No. 9 a, b + 4c, d

The same, 1.815

FACE 06

Consumptioncementsolutionon 100 PCS. blocks(mortarbed), m 3

Note. The values ​​of the factors are framed in the table , which are calculated on the basis of this technological map .