Yenir Collection E6. Carpentry and carpentry work in buildings and facilities
B. Device of roofs from collection rafting shields and farms
The composition of the work
1. Cutting roofing on ribbons and laying ribbons under Mauerlas and lining. 2. Laying Mauerlatov. 3. Laying angular runs. 4. Laying of support elements. 5. Manufacture and laying of lining. 6. Installation of support farms. 7. Installation of lower rafting shields. 8. Strengthening reference farms, lower rafting shields and rafted with wire twists with a drip in the tin masonry. 9. Installation of upper farms. 10. Installation of cage shields. 11. Installing the mare. 12. Cornery Oveset Corners. 13. Removing diagonal boxes. 14. Studying. 15. Manufacturing and installation of subposses. 16. Production and installation of racks for diagonal rafting legs. 17. Production and production of these people. 18. Cruccake rafted Brucki. 19. Installing the ski board. 20. Device auditory windows With a slit of openings in the crate. 21. Device dissection near pipes.
Table 3.
Time norms and rates per 100 m 2 roof slide
The composition of the link of carpenters |
N.VR. |
Frame |
4 dollars-2 |
20-86 |
|
3 "-2 |
B. Farm Installation and Farm Coating Device
The composition of the work
1. Terminating designs. 2. Lifting structures using a tower crane and installation in a design position. 3. Temporary mount. 4. Distribution and final consolidation.
Table 4.
The composition of the link |
For farms flying, m |
|
up to 15 and composite beams |
st. 15. |
|
Crane operator |
||
(Cranewner) 5 disc. |
1 |
1 |
Carpenter 6 " |
- |
1 |
"5 " |
1 |
- |
"4 " |
2 |
2 |
"3 " |
3 |
3 |
Table 5.
Time standards and rates for 1 farm or beam
Designs |
N.VR. Frame |
for |
||
machineist |
carpenters |
|||
Farm by fly, m |
up to 15 |
0,68 0-61,9 |
4,08 3-12 |
|
up to 20. |
0,9 0-81,9 |
5,4 4-27 |
||
sv. twenty |
1,4 1-27 |
8,4 6-64 |
||
The beams of the compound section |
0,56 0-51 |
3,36 2-57 |
||
G. Laying of runs, Device of flooring and frame frames
The composition of the work
When laying runs
1. Production and fit of interfaces of joints in bars or composite runs from boards. 2. Production of framed beams. 3. Drilling holes for bolts. 4. Laying runs on farms with fixings.
When the devices are devices for runs
1. Receive packets with materials. 2. Laying of boards or rails on runs with a climbing in the joints and on the Outs. 3. Fingering with nails. 4. Trimming the ends of boards or rails protruding behind the edges of the skates.
When device frames lanterns
1. Marking and manufacture of elements in templates with the manufacture of all pairs. 2. Marking and drilling of bolted holes. 3. Assembling the frame with a fit of mating between themselves and with supports. 4. Prsk, reconciliation and extension of the installed frame. 5. Complete bolts and fixing nails.
Table 6.
Designs |
The composition of the link |
Meter |
N.VR. |
Frame |
|||
Runs |
from bars or two boards |
Carpenters: |
100 meters |
21-74 |
|||
5 Disma - 1. |
runs |
||||||
3 "- 1 |
|||||||
of the three boards |
Also |
Also |
34-62 |
||||
Flooring |
working |
Carpenters: |
100 m 2. |
15,5 |
11-55 |
||
4 Disma - 1. |
floor |
||||||
3 "- 1 |
|||||||
protective |
flat |
Also |
Also |
18,5 |
13-78 |
||
curvilinear |
17-14 |
||||||
Carcasses |
from Bruschev |
Carpenters: |
100 meters |
39,5 |
31-80 |
||
lantern |
5 Disma - 1. |
bRUSEV B. |
|||||
3 "- 1 |
business |
||||||
from the board |
Also |
100 m boards in business |
18,5 |
14-89 |
Notes: 1. N.VR. and Frame Table. 5 Multiply multiplied with structures: with help manual winches by 2.5 (PR-3); with the help of electrolyboys by 1.7 (PR-4); With the help of cranes on a pneumocole move and automotive cranes by 1.1 (PR-5). 2. When installing three-starry arches N.VR. and Frame Rows N 1-3 Table. 5 Multiply by 2.25 (PR-6). This coefficient takes into account the installation of suspensions, fumes, hinges and moving of mounting forests. 3. Installation, moving and mast cleaning, as well as movement of structures on rinks with Table stands. 5 and 6 are not taken into account and normalized by the collection of E25 "rigging work".
§ E6-10. Laying of fibrous plates
on reinforced concrete coating plates
The composition of the work
1. Cleaning the coating plates. 2. Applying a layer of finished mastic. 3. Sticker of wood-fiber plates with refreshing plates in the necessary cases. 4. Pouring seams.
Time norms and rates for 1 m 2 coatings
The composition of the link |
Laying of fibrous plates |
|
two layers |
four layers |
|
Insulator on thermal insulation: |
||
4 Disma - 1. |
0,16 |
0,3 |
3 "- 2 |
0-11,3 |
0-21,2 |
2 "- 1 |
||
§ E6-11. Knocking Kornizov
The composition of the work
1. Sewing ready-made mare. 2. Stroging stitching. 3. Pribration of finished cartoons.
Time rate and Pricing for 100 MDOs
§ E6-12. Device of porch pads, stairs, terraces, veranda and tambourists
The composition of the work
When installing the porch on ready base
1. Assembling the porch from the finished parts. 2. Installing the porch on the finished base, checking the correctness of the installation and fastening.
When installing the porch with the device Basis
1. Billet chairs with applying antiseptic compositions. 2. Installing chairs in ready-made pits and madness. 3. Laying the nozzles with reconciliation. 4. The device flooring site and trim from sides.
During the device steps, Tumb and visors of the porch, terraces and veranda
1. Production of the guards, Tumb. 2. Assembling stairs from ready-made details. 3. Installing a tumb with their boards. 4. Production and assembly of a single visor with wooden brackets and a solid roof dryer.
When applying stairs with platforms
1. Installation of beams, racks and platforms. 2. Word in the beams of bars for maintaining the floor. 3. Production of wrinkles in the genital and field beams of compounds with marches. 4. Installation of marches. 5. Alignment of the position of the marches. 6. Favoring stairs and playgrounds. 7. Installation of the rail.
With the device Tambura
1. Floor outline with fit boards or boards. 2. Installing side shields with fastening. 3. The tambour roof device from shields with nails fastening. 4. Fit and hitch entrance door Tambura.
When appliance terraces and veranda
1. Overall and butterfit racks and open parts of the strapping. 2. Outlet of boards and bars. 3. Preparation of elements with a step. 4. Conjugation billet. 5. Figure Filovka. 6. Refecting the installation of the chairs. 7. Connection of strapping in the corners with mounting to chairs with nails. 8. Staying of boardy beams of two boards and struts, between beams with their feeding to the beams of nails. 9. Laying of floorboards with nails in each intersection with beams and with a fit of them in places connections with racks. 10. Installation of finished clean racks. 11. Laying the upper strapping on nails feeding. 12. Laying ceiling beams. 13. Installing the rafter feet with a fit in places of adjustment to upper strapping, with the strengthening of another end to the wall of the house. 14. A clean carnis device with the installation of kills, feeding and connecting boards in the corners, with the lining of the lumps by the mare. 15. Ceiling cover on the beams.16. Dooming rafters with nails feeding boards. 17. Cleaning the base with clean boards. 18. Assembly and installation of fences from finished elements with strengthening. 19. Installation and strengthening of single deaf window bakes, fit and soda door Towns (with a veranda device).
Table 1
The composition of the link |
Designs |
|
clean stairs |
others |
|
Carpenter 5 breaks |
||
"4 " |
||
"3 " |
table 2
Time norms and rates for the meters specified in the table
Designs |
Meter |
N.VR. |
Frame |
||
Porch playground |
on the finished basis |
1 porch |
3,7 |
2-76 |
|
with a base device |
also |
5,6 |
4-17 |
||
Steps |
1 step |
2,6 |
1-94 |
||
Two stands with their boards |
1 porch |
1,8 |
1-34 |
||
Single visors with wooden brackets and a solid roof crate |
also |
8,2 |
6-11 |
||
clean with platforms and staircase |
1 m Marsha |
1,8 |
1-45 |
||
Stairs |
caidial without bearing |
also |
0,85 |
0-63,3 |
|
the same, with staircase staircase |
1,1 |
0-82 |
|||
Tambura entrance |
1m 2 floor |
1,7 |
1-27 |
||
from three sides with an adjuncing to the house with one side |
also |
3-73 |
|||
from three sides, under the finished overall roof house |
4,6 |
3-43 |
|||
Terraces open |
on both sides (with the bedtop to the house with two sides) |
4,2 |
3-13 |
||
on the one hand with an adjuncing to the house with three parties |
3,8 |
2-83 |
|||
with an adjuncing to the house with one side |
5,9 |
4-40 |
|||
Veranda closed |
under the finished shared with the house of the roof (with an adjuncing to the house with one side) |
5,3 |
3-95 |
||
with the adjuncing to the house with two sides |
4,7 |
3-50 |
|||
with an adjuncing to the house with three parties |
2-98 |
Notes: 1. Row standards N 1 and 2 are provided for the device of the porch area to 2.5 m 2 . With a larger area of \u200b\u200bthe porch for each 1 m 2 add N. Ver. 1.4 people, h, Frame 1-04 (PR-1). 2. Under the device, the veranda of the workpiece of parts and the assembly of single deaf bindings and light doors is not provided and is charged additionally.
§ E6-13. Filling opening
The composition of the work
When installing blocks
1. Clearing the base of the opening. 2. Terminating block when tap is installed. 3. Block factory in the opening or installation along the laying in the design position. 4. Unimbilling the installation. 5. Swim block with blank wedges. 6. Fastening the block of a block to the wall of the rams.
When installing boxes
1. Cleaning the base of the opening from the frozen solution. 2. Installing the box with verification of the installation on the plumb and the level. 3. Fastening the box to the wall of the hershams.
When installing windows
1. Clearing the furrows (when installing windowsill in stone walls). 2. A fit of the windows board at the place. 3. Applying antiseptic compositions and upholstery by felt. 4. Installation and level check. 5. Fastening the windows.
Add when installed on wooden brackets:
6. Production and installation of wooden brackets.
Add when installed on metal brackets:
6. Marking and dumping manually two sockets in the box of the window block (places of fastening metal brackets). 7. Installing brackets with fastening screws to the box.
When installing mounting boards
1. Cleaning the base of the opening of the frozen solution (when installed in stone walls). 2. Fit boards at the place. 3. Installing the mounting boards to the place with the trim and felt and the level reconciliation.
When the gate is hung
1. A fit of the gates of the goal in place. 2. The formulation of blacksmithing loops and hooks with drilling holes and fastening bolts. 3. Staging and strengthening grazing. 4. Hit the gate on the hook.
When the gate is hiding with the automotive crane
1. Marking of places for the installation of hooks (lylish). 2. Locking the goal sash. 3. Putting the gate sash in the openings. 4. Hit the gate of the gate on the hook. 5. Removing the correctness of the set of the gate.
At electric welding
1. Fastening the hooks to the electric welding box.
When setting metal squares
1. Marking and drilling holes. 2. Staging the bolts on bolts.
When having carpentry doors
1. Cliff and fit door cloths to the impeller. 2. Staging and strengthening loops on screws. 3. The setting of instruments and the doorway of the doors on the loop.
The composition of the link
A. For table. 1 rows N 2-7 and Table. 4 lines N 3 and 4
B. For Table 1 Rows N 1, Tables 2 and 3 (FULL); Table. 4 lines N 1, 2 and 7-11
B. For table. 4 lines N 5
Electric welder manual welding 3 raz. - one
G. for table. 4 lines N 6
Carpenter 3 breaks - one
A. Installation OKOHHHHBIX and Door Blocks
Table 1
Time norms and rates for 100 m 2 Square of blocks (by outdoor vehicle)
Block area, m 2 , before |
With narrow single boxes (with single or tweed binders) |
With wide or composite boxes (with two separate bindings) |
|||
N.VR . Frame |
for |
N.VR. Frame |
for |
||
machineist |
carpenters |
machineist |
carpenters |
||
51 36-47 |
59 42-19 |
||||
1,5 |
10,5 9-56 |
21 15-02 |
12,5 11-38 |
25 17-88 |
|
9 8-19 |
18 12-87 |
11 10-01 |
22 15-73 |
||
2,5 |
8 7-28 |
16 11-44 |
10 9-10 |
20 14-30 |
|
6,7 6-10 |
13,4 9-58 |
7,8 7-10 |
15,6 11-15 |
||
3,5 |
6,2 5-64 |
12,4 8-87 |
7,4 6-73 |
14,8 10-58 |
|
4 and St. |
5,7 5-19 |
11,4 8-15 |
6,7 6-10 |
13,4 9-58 |
|
B. Installation of boxes
table 2
Time norms and rates per 100 m area of \u200b\u200bthe box (by outdoor survey)
Box area, m 2 , before |
Window boxes |
Door boxes |
|||
narrow |
wide or composite |
narrow |
wide or composite |
||
35 25-03 |
47 33-61 |
26 18-59 |
34 24-31 |
||
1,5 |
24,5 17-52 |
32 22-88 |
26 18-59 |
34 24-31 |
|
20,5 14-66 |
27 19-31 |
23 16-45 |
30 21-45 |
||
2,5 |
18,5 13-23 |
24 17-16 |
20 14-30 |
4 |
|
3 |
16 11-44 |
21 15-02 |
17 12-16 |
5 |
|
3,5 |
15,5 11-08 |
20 14-30 |
21 15-02 |
6 |
|
4 |
13,5 9-65 |
17,5 12-51 |
14,5 10-37 |
7 |
|
4.5 and St. |
12,5 8-94 |
16,5 11-80 |
8 |
||
but |
b. |
in |
g. |
N. |
B. Installation of subcasts And mounting boards
Table 3.
Time norms and rates for the meters specified in the table
Product |
Meter |
N.VR. |
Frame |
N. |
|
without brackets |
1 m board |
0,14 |
0-10 |
1 |
|
Window boards |
on wooden brackets |
also |
0,21 |
0-15 |
2 |
on metal brackets |
" |
0,31 |
0-22,2 |
3 |
|
Mounting boards in openings industrial buildings |
1 board |
0,21 |
0-15 |
4 |
Gorodnaya Gate And carpentry doors
Table 4.
Time norms and rates for the meters specified in the table
Product |
Meter |
N.VR. |
Frame |
N. |
||
Gate when installed |
single holders |
1m 2 Towels |
0,45 |
0-32,2 |
1 |
|
manually |
double-spin |
also |
0,62 |
0-44,3 |
2 |
|
Gate As |
snack |
for driver |
" |
0,12 |
0-10,9 |
3 |
installation |
for carpenters |
" |
0,24 |
0-17,2 |
4 |
|
crane |
fastening the hooks and lying to the electric welding box |
1 hook or eye |
0,05 |
0-03,5 |
5 |
|
galnikov production |
1 Galnik |
0,43 |
0-30,1 |
6 |
||
Carpentry doors |
on mortise swords or in |
single holders |
1m 2 Loves |
0,24 |
0-17,2 |
7 |
tip |
double-spin |
also |
0,41 |
0-29,3 |
8 |
|
on Plancks |
single holders |
" |
0,16 |
0-11,4 |
9 |
|
double-spin |
" |
0,29 |
0-20,7 |
10 |
||
on swinging loops |
" |
0,65 |
0-46,5 |
11 |
Notes: 1. Na Dolbing two nests in the threshold for doorless boxes take 1 box N.VR. 0.13 people, Frame 0-09.3 (PR-1). 2. Drying the bindings and door cloths in the box installed in the location in the table. 2 § E40-3-23 "Production wooden structures and parts "taking into account clause 1 of the introductory part. 3. Table 1 standards of strings N 1 The installation of blocks manually is provided, and the rows N 2-7 - a crane. When installing blocks manually N.Ver. and Frame For carpenters of strings N 2-7 multiply by 1.7 (PR-2). Table 2 standards Installation of boxes are provided manually. 4. The production of work is provided at an altitude of up to 15 m from the ground level, in the production of work at the height of St. 15 m for each subsequent meter of the height of N.VR. and Frame Increase by 0.5% (PR-3). 5. Table stands. 1 Provides construction of structures tower crane Or the truck crane, the standards of strings N 3 and 4 Table 4 - only a tower crane. When installing autocrante N.Ver. and Frame These lines are multiplied by 1.1 (PR-4). 6. When installing blocks in wooden walls Without impact of the ridge at the ends of Proshezkov N. Ver. and Frame Table 1 Multiply 1.15 (PR-5). 7. Overviews breeding walls Finished parts of the deck and ready-made blocks with a ridge on the ends of the elders are normalized by example.2 § E6-6. 8. When installing blocks with glazed window bindings or door leafs N.VR. and Frame Table 1 Multiply to 1.15 (PR-6). 9. When installing unfolded blocks N. Ver. and Frame Table. 1 Multiply by 1.2 (PR-7). 10. On the removal from the loops of previously hung windows of non-beams, framug and doorbells with unscrewing loops, with a reverse sample of them and screwing the loops to take on 1 sash or Framuhu N. Ver. 0.12 people, h, Frame 0-08.6 (PR-8); On 1 door leaf N.VR. 0.23 people, h, Frame 0-16,4 (PR-9). With removable hinges, take: on 1 sash or 1 fraamuga - N.VR. 0.04 people, h, Frame 0-02.9 (PR-10); on 1 doorbeal - N.VR 0.07 people, Frame 0-05 (PR-11). 11. The pantry of single and double boxes of dry packles is normalized by the collection of E8-1 "Finishing Works".
§ E6-14. Stirling elements filling opening
The composition of the work
1. Marking places squaling. 2. Removing the opening elements (door leaf, window sash, Framuga or Forms) with loops. 3. Removing larvae, valves, cards, loops and forwarding (if necessary). 4. Stirring elements and fit at place. 5. Installation of larvae, valves, cards, loops and guidelines in place, partial recess of the sockets (if necessary). 6. Hitting the elements of the filling of openings.
Construction joiner - 5 disc.
Time norms and rates for the meters specified in the table
Product |
Meter |
N.VR. |
Frame |
N. |
|
Window blocks with paired |
1,5 |
1 block |
0,33 |
0-30 |
1 |
binders at the Ocement Square, m 2 , before |
2,1 |
also |
0,47 |
0-42,8 |
2 |
2,5 |
" |
0,59 |
0-53,7 |
3 |
|
3,2 |
" |
0,73 |
0-66,4 |
4 |
|
Balcony door blocks with paired polls |
" |
0,34 |
0-30,9 |
5 |
|
Window paired fraamuga and windows at the area, m 2 , before |
0,2 |
1 Framuga or Fortochka |
0,18 |
0-16,4 |
6 |
0,3 |
also |
0,24 |
0-21,8 |
7 |
|
sv. 0,3. |
" |
0,27 |
0-24,6 |
8 |
|
Window sash on removable and detachable |
1 |
1 sash |
0,2 |
0-18,2 |
9 |
loops with separate bindings |
1,5 |
also |
0,24 |
0-21,8 |
10 |
square, M. 2 , before |
2 |
" |
0,27 |
0-24,6 |
11 |
2,5 |
" |
0,31 |
0-28,2 |
12 |
|
The same, on hinged loops (with |
1 |
" |
0,25 |
0-22,8 |
13 |
unscrewing and screwing screws) |
1,5 |
" |
0,3 |
0-27,3 |
14 |
at the sash area of \u200b\u200bfraumuga or |
2 |
" |
0,35 |
0-31,9 |
15 |
forms, M. 2 , before |
2,5 |
" |
0,41 |
0-37,3 |
16 |
Door blocks at the opening area, m 2 , before |
2 |
1 block |
0,26 |
0-23,7 |
17 |
2,5 |
also |
0,33 |
0-30 |
18 |
|
3 |
" |
0,43 |
0-39,1 |
19 |
|
3,5 |
" |
0,53 |
0-48,2 |
20 |
|
4 |
" |
0,67 |
0-61 |
21 |
|
sv. four |
" |
0,81 |
0-73,7 |
22 |
|
Doors of built-in and antlesol wardrobes |
0,3 |
1 Polit |
0,13 |
0-11,8 |
23 |
square, M. 2 , before |
0,5 |
also |
0,14 |
Unified norms and rates for construction,
Mounting and repair and construction work
Collection E6.
Carpentry and carpentry work
In buildings and facilities
Developed by the Central Republican Regulatory Station (TsRNIS) Rosagropromstroy under the Methodological Guidelines and with the participation of the Central Bureau of Labor Regulations in Construction (CBNC) when working in the construction of the USSR State Building.
Approved for use in construction and installation, repair and construction and equivalent organizations, as well as in divisions (brigades, sites) of industrial associations, enterprises, organizations and institutions engaged in construction and overhaul The economic method translated into new conditions for remuneration of employees in accordance with the Decree of the Central Committee of the CPSU, the Council of Ministers of the USSR and the Central Bank institution "On Improvement and Organization wages and the introduction of new tariff rates and official salaries of employees of the production sectors of the national economy. "
The production technology provided for in the collection was agreed with the Rosagropromstroy Technical Center.
Input part
1. The norms of this discharge are provided for the assembly, installation of wooden parts of buildings (structures) and processing of timber.
Work on the mechanized processing of timber, the manufacture of parts and constructive elementsExcept for the cases stipulated in this collection are normalized by the issue of the E40 collection of wooden structures and parts.
2. In the production of carpentry and carpentry work, it is necessary to comply with the following requirements: surface treatment care; conjugation density; accuracy of compliance with design sizes and shapes; the choice and correctness of the use of wood, varieties and sizes of materials in accordance with the type and responsibility of the structures; Performing works on the protection of wooden structures from fire, rotting and damage to fungal destroyers.
3. In addition to the main operations specified in the work of the main operations, all auxiliary operations are taken into account, such as, for example, the selection and markup of materials and parts, peeling, climbing and fitting, setting metal fasteners, drilling holes, easy smacking on potted stairs, stepladers and kids, etc., point and editing of tools, caring for manual and mechanized tool In the process of work, quality control of work, the movement of materials, parts and devices up to 30 m to the horizontal path (with the exception of particularly stipulated cases).
4. Digging holes for installing wooden elements (chairs, pillars, racks, etc.) norms are not provided and normalized by the statement of the collection E2 "Mechanized And manual earthworks. "
5. When disassembling non-inventory temporary and auxiliary devices Related N.VR. and plenty . Multiply to the safety of timber laid in the stack, from 96 to 100% - by 1.5 (RF -1) and from 81 to 95% - by 1.25 (RF -2). Ceffs to N.Vr. and plenty . Used in the presence of appropriate documents for the posting of the valid timber from the disassembly of temporary buildings, structures and devices.
With the safety of timber from 65 to 80% N.VR. and plenty . The corresponding paragraphs are applied unchanged. With the safety of timber less than 65%, the work is considered to be a marriage if the specified figure is not specified in the task.
6. Rates for machinists are calculated by tariff rate 5 rav. When installing designs with cranes, driven by machiners 4 or 6, the rates for machinists should be recalculated by tariff rates corresponding to 4 or 6 solutions. In accordance with the ETKS works and professions of workers, state 3, section. "Construction, assembly and repair and construction work", approved on July 17, 1985.
7. Performance of work in cramped conditions is taken into account by the standards for appropriate work and additional payment is not subject to.
8. The norms are provided for the use of a bold forest.
9. The rules provide for the implementation of work using soft rocks (pines, spruce, fir, etc.). With the use of timber materials of other breeds N. Ver. and Frame (except Section "A" § E6-6) multiplied by the coefficients shown in the table.
Yenir
§ E6-13. Filling opening
The composition of the work
When installing blocks
1. Clearing the base of the opening.
2. Terminating block when tap is installed.
3. Block factory in the opening or installation along the laying in the design position.
4. Unimbilling the installation.
5. Swim block with blank wedges.
6. Fastening the block of a block to the wall of the rams.
When installing boxes
1. Cleaning the base of the opening from the frozen solution.
2. Installing the box with verification of the installation on the plumb and the level.
3. Fastening the box to the wall of the hershams.
When installing windows
1. Clearing the furrows (when installing window sills in stone walls).
2. A fit of the windows board at the place.
3. Applying antiseptic compositions and upholstery by felt.
4. Installation and level check.
5. Fastening the windows.
Add when installed on wooden brackets:
6. Production and installation of wooden brackets.
Add when installed on metal brackets:
6. Marking and dumping manually two sockets in the box of the window block (places of fastening metal brackets).
7. Installing brackets with fastening screws to the box.
When installing mounting boards
1. Cleaning the base of the opening of the frozen solution (when installed in stone walls).
2. Fit boards at the place.
3. Installing the mounting boards to the place with the trim and felt and the level reconciliation.
When the gate is hung
1. A fit of the gates of the goal in place.
2. The formulation of blacksmithing loops and hooks with drilling holes and fastening bolts.
3. Staging and strengthening grazing.
4. Hit the gate on the hook.
When the gate is hiding with the automotive crane
1. Marking of places for the installation of hooks (lylish).
2. Locking the goal sash.
3. Putting the gate sash in the openings.
4. Hit the gate of the gate on the hook.
5. Removing the correctness of the set of the gate.
At electric welding
1. Fastening the hooks to the electric welding box.
When setting metal squares
1. Marking and drilling holes.
2. Staging the bolts on bolts.
When having carpentry doors
1. Cliff and fit door cloths to the impeller.
2. Staging and strengthening loops on screws.
3. The setting of instruments and the doorway of the doors on the loop.
The composition of the link
A. For table. 1 rows N 2-7 and Table. 4 lines N 3 and 4
B. For Table 1 Rows N 1, Tables 2 and 3 (FULL); Table. 4 lines N 1, 2 and 7-11
B. For table. 4 lines N 5
Electric welder manual welding 3 raz. - one
G. for table. 4 lines n 6
Carpenter 3 breaks - one
A. Installation OKOHHHBIX and Door Blocks
Table 1
Time norms and rates for 100 m² blocks of blocks (by outdoor surger)
Block area, m 2, to | With narrow single boxes (with single or tweed binders) | With wide or composite boxes (with two separate bindings) | |||
N.VR. Frame |
for | N.VR. Frame |
for | ||
machineist | carpenters | machineist | carpenters | ||
1 | — | 51 | — | 59 | 1 |
1,5 | 10,5 | 21 | 12,5 | 25 | 2 |
2 | 9 | 18 | 11 | 22 | 3 |
2,5 | 8 | 16 | 10 | 20 | 4 |
3 | 6,7 | 13,4 | 7,8 | 15,6 | 5 |
3,5 | 6,2 | 12,4 | 7,4 | 14,8 | 6 |
4 and St. | 5,7 | 11,4 | 6,7 | 13,4 | 7 |
but | b. | in | g. | N. |
B. Installation of boxes
table 2
Time norms and rates for 100 m² of the area of \u200b\u200bthe box (by outdoor)
Box area, m 2, to | Window boxes | Door boxes | |||
narrow | wide or composite | narrow | wide or composite | ||
1 | 35 | 47 | 26 | 34 | 1 |
1,5 | 24,5 | 32 | 26 | 34 | 2 |
2 | 20,5 | 27 | 23 | 30 | 3 |
2,5 | 18,5 | 24 | 20 | 4 | |
3 | 16 | 21 | 17 | 5 | |
3,5 | 15,5 | 20 | 21 | 6 | |
4 | 13,5 | 17,5 | 14,5 | 7 | |
4.5 and St. | 12,5 | 16,5 | 8 | ||
but | b. | in | g. | N. |
B. Installation of subcast and mounting boards
Table 3.
Product | Meter | N.VR. | Frame | N. | |
without brackets | 1 m board | 0,14 | 0-10 | 1 | |
Window boards | on wooden brackets | also | 0,21 | 0-15 | 2 |
on metal brackets | « | 0,31 | 0-22,2 | 3 | |
Mounting boards in the openings of industrial buildings | 1 board | 0,21 | 0-15 | 4 |
Mr. Hit the gate and carpentry doors
Table 4.
Time norms and rates for the meters specified in the table
Product | Meter | N.VR. | Frame | N. | ||
Gate when installed | single holders | 1 m 2 Cloths | 0,45 | 0-32,2 | 1 | |
manually | double-spin | also | 0,62 | 0-44,3 | 2 | |
Gate As | snack | for driver | « | 0,12 | 0-10,9 | 3 |
installation | for carpenters | « | 0,24 | 0-17,2 | 4 | |
crane | fastening the hooks and lying to the electric welding box | 1 hook or eye | 0,05 | 0-03,5 | 5 | |
galnikov production | 1 Galnik | 0,43 | 0-30,1 | 6 | ||
Carpentry doors | on mortise swords or in | single holders | 1 m 2 canvas | 0,24 | 0-17,2 | 7 |
tip | double-spin | also | 0,41 | 0-29,3 | 8 | |
on Plancks | single holders | « | 0,16 | 0-11,4 | 9 | |
double-spin | « | 0,29 | 0-20,7 | 10 | ||
on swinging loops | « | 0,65 | 0-46,5 | 11 |
Notes: 1. Na Dolbing two nests in the threshold for doorless boxes take 1 box N.VR. 0.13 people.-H, full 0-09.3 (PR-1). 2. Drying the bindings and door cloths in the box installed in the location in the table. 2 § E40-3-23 "Production of wooden structures and parts" taking into account paragraph 1 of the introductory part. 3. Table 1 standards of strings N 1 provides installation of blocks manually, and rows N 2-7 - crane. When installing blocks manually N.Ver. and all For carpenters of strings N 2-7 multiply by 1.7 (PR-2). Table 2 standards Installation of boxes are provided manually. 4. The production of work is provided at an altitude of up to 15 m from the ground level, in the production of work at the height of St. 15 m for each subsequent meter of the height of N.VR. and all Increase by 0.5% (PR-3). 5. Table stands. Figure 1 provides a tower crane or autocrante design, string standards N 3 and 4 Table 4 - only with a tower crane. When installing autocrante N.Ver. and all These lines are multiplied by 1.1 (PR-4). 6. When installing blocks into wooden walls without multipling the ridge on the ends of the simplicity of N. Ver. and all Table 1 Multiply 1.15 (PR-5). 7. The extension of the loaders of the log walls with finished parts of the deck and finished blocks with a ridge of the ridge on the ends of the sinks are normalized according to NOTE.2 § E6-6. 8. When installing blocks with glazed window bindings or door leafs N.VR. and all Table 1 Multiply to 1.15 (PR-6). 9. When installing unfolded blocks N. Ver. and all Table. 1 Multiply by 1.2 (PR-7). 10. On the removal from the loops of previously hung windows of non-beams, framug and doorbells with unscrewing loops, with a reverse sample of them and screwing the loops to take on 1 sash or Framuhu N. Ver. 0.12 people-h, FRI. 0-08.6 (PR-8); On 1 door leaf N.VR. 0.23 people, hts 0-16.4 (PR-9). With removable hinges, take: on 1 sash or 1 fraamuga - N.VR. 0.04 people, hts. 0-02.9 (PR-10); on 1 doorbeal - N.VR 0.07 people.-H, FRI. 0-05 (PR-11). 11. Pancathing of single and double boxes of dry packles rationed by the collection of E8-1 "Finishing works".
Yenir
Unified norms and rates for construction,
Mounting and repair and construction work
Collection E6.
Carpentry and carpentry work
In buildings and facilities
Developed by the Central Republican Regulatory Station (TsRNIS) Rosagropromstroy under the Methodological Guidelines and with the participation of the Central Bureau of Labor Regulations in Construction (CBNC) when working in the construction of the USSR State Building.
Approved for use in construction and installation, repair and construction and equivalent organizations, as well as in divisions (brigades, sites) of production associations, enterprises, organizations and institutions engaged in construction and overhaul of the economic method translated into new conditions for remuneration of employees In accordance with the decision of the Central Committee of the CPSU, the Council of Ministers of the USSR and the Central Bank institution "On the improvement and organization of wages and the introduction of new tariff rates and official salaries of workers in the production sectors of the national economy."
The production technology provided for in the collection was agreed with the Rosagropromstroy Technical Center.
Input part
1. The norms of this discharge are provided for the assembly, installation of wooden parts of buildings (structures) and processing of timber.
Works on the mechanized processing of timber, the manufacture of parts and structural elements, except in cases specified in this collection, are ignored by vol. 3 collection E40 "Production of wooden structures and parts".
2. In the production of carpentry and carpentry work, it is necessary to comply with the following requirements: surface treatment care; conjugation density; accuracy of compliance with design sizes and shapes; the choice and correctness of the use of wood, varieties and sizes of materials in accordance with the type and responsibility of the structures; Performing works on the protection of wooden structures from fire, rotting and damage to fungal destroyers.
3. In addition to those specified in the work of the main operations with the norms, all auxiliary operations are taken into account, such as, for example, the selection and markup of materials and parts, repellent, clutch, and fitting, laying metal fasteners, drilling holes, easy to smashing on the withdrawal stairs, stepladers and kids and t . p., Point and editing of tools, caring for manual and mechanized instrument in the process of work, quality control of work, movement of materials, parts and devices up to 30 m to the horizontal path (with the exception of particularly specified cases).
4. Digging holes for the installation of wooden elements (chairs, pillars, racks, etc.) norms are not provided and normalized by the statement of the collection E2 "mechanized and manual earthworks".
5. When disassembling non-inventory time and auxiliary devices, the corresponding N.VR and Frame Multiply with the safety of timber laid in a stack, from 96 to 100% - by 1.5 (HF-1) and from 81 to 95% - by 1.25 (HF-2). Ceffs to N.Vr. and Frame Used in the presence of appropriate documents for the posting of the valid timber from the disassembly of temporary buildings, structures and devices.
With the safety of timber from 65 to 80% N.VR. and Frame The corresponding paragraphs are applied unchanged. With the safety of timber less than 65%, the work is considered to be a marriage if the specified figure is not specified in the task.
6. Rates for machinists are calculated at the tariff rate of 5 disc. When installing designs with cranes, driven by machiners 4 or 6, the rates for machinists should be recalculated by tariff rates corresponding to 4 or 6 solutions. In accordance with the ETKS works and professions of workers, state 3, section. "Construction, assembly and repair and construction work", approved on July 17, 1985.
7. Performance of work in cramped conditions is taken into account by the standards for appropriate work and additional payment is not subject to.
8. The norms are provided for the use of a bold forest.
9. The rules provide for the implementation of work using soft rocks (pines, spruce, fir, etc.). With the use of timber materials of other breeds N. Ver. and Frame (except Section. "A" § E6-6) Multiply the coefficients shown in the table.
Name |
Coefficients for |
|
work |
solid hardwood (oak, ash, ram, beech, etc.) |
middle hardness breeds (larch, birch, etc.) |
Treatment of timber manual |
1.5 (RF-3) |
1.25 (RF-4) |
Assembly and installation of wooden parts of buildings and structures |
1,2 (HF-5) |
1.1 (HF-6) |
10. In the production of carpentry and joinery, it must be strictly followed by the safety requirements provided for by SNiP W-4-80.
Chapter 1. Forests, overpass, scaffolding and stepladers
§ E6-1. Inventory forests and overpass
The composition of the work
When installing forests and overpass
1. Layout of forest installation location and lining laying (Lag). 2. Installation and assembly of forest elements and a hoist. 3. Foresting forests to the wall, punching the nests, the installation of traffic jams and anchors. 4. The device flooring from shields after 2 m in height. 5. Installation of stepladders and fences. 6. Lifting elements on the necessary height using a block.
When disassembling forests and a hoist
Disassembly of forests and overpass with descent, sorting and stacking elements in the stack.
Table 1
The composition of the link |
Rooms Points |
||
a-G. |
e-Z. |
||
Installer on the installation of steel and reinforced concrete structures: |
|||
4 rally |
|||
3 " |
|||
2 " |
|||
Carpenter 5 breaks |
|||
" 4 " |
|||
" 3 " |
|||
" 2 " |
Fig.1. Knot connect elements in tubular forests on hinged clamps
1 - clamp; 2 - cross; 3 - Stand
Fig.2. Knot connecting elements in stingy tubular forests
1 - cross; 2 - run; 3 - hook; 4 - nozzle; 5 - Stand
Fig. 3. Connection node of elements in tubular forests on brackets
1 - cross; 2 - bracket; 3 - rack; 4 - Bolt.
table 2
Time standards and rates for 1 m 2 forest projections on the wall (for Count "A" - "D"),
on 1 m forests in length (for the Count "E") and 1 m 2 flooring (for the Count "F" and "s")
Type of facilities |
Metal forests |
Wood forests |
Outacades with flooring from plates or boards |
||||||
with the connection of tubular elements |
suspended string |
on frame, rack and fermented supports |
prom |
on metal frames |
on the wooden supports |
||||
on hinge clamps |
in stupid forests |
on braces |
|||||||
Device |
0,25 0-17,7 |
0,23 0-16,3 |
0,44 0-31,1 |
0,38 0-26,9 |
0,35 0-26,6 |
0,96 0-67,9 |
0,71 0-50,2 |
0,97 0-68,6 |
|
Disassembly |
0,15 0-10,6 |
0,13 0-09,2 |
0,23 0-16,3 |
0,19 0-13,4 |
0,17 0-12,9 |
0,47 0-33,3 |
0,59 0-41,7 |
0,82 0-58 |
|
Notes: 1. Table standards. 2 takes into account the buildup of the racks when equipped with wooden forests (except for graduation) and overpass. When equipped with wooden forests (except for graduation) and overpass without building racks N. Ver. and Frame Multiply by 0.9 (PR-1). 2. The device of forests from the subsidations of buildings is normalized according to the standards of Table. 2, 3. Small repair of forest elements up to 10% total Elements and details performed in the process of installing forests, normalize according to the corresponding graphs, multiplying N.VR. and Frame 0.1 (PR-2). 4. In tab. 2 There are comprehensive norms for assembly, disassembling forests with a device and disassembly of the shield flooring. When separately assembling and disassembling metal details of forests and shield, waged wage can be made separately taking into account the complexity of each of these works in Table 3. 5. Table stands. 2 The device and disassembly of inventory forests are provided, except for the graduation, with a filling after 2 m. With a height between the flooring of 1.2 m, the corresponding N.VR and Frame Multiply by 1.65 (PR-3). 6. Table stands. 2 It is provided for the height of the forests up to 16 m, counting from the base (the lower plane of the lining under the rack) to the top flooring. With a high altitude of forests N.VR. and Frame Table. 2 on the device and disassembly of forests, in addition to the graduation, to increase for each of the following 4 M of forest heights (with a distance between the flooring 2 m) or every 2.4 m (at the flooring after 1.2 m) by 15% (PR-4), Determining the number of areas with a height of 4 m or 2.4 m with rounding to a larger integer.
Table 3.
Labor consumption,% |
||||
The woods |
when assembling |
when disassembling |
||
metal details |
shield flooring |
metal details |
shield flooring |
|
On hinge clamps or brackets |
||||
On stupid connections |
||||
Suspended string |
§ E6-2. Non-inventary forests
A. Production
The composition of the work
1. Marking and transverse repellent materials. 2. Production of conjugates of all types with dumping, stuffing and device.
The composition of the link
A carpenter |
4 |
range |
- 1 |
" |
3 |
" |
- 1 |
" |
2 |
" |
- 2 |
Table 1
Forests are indigenous |
Meter |
N.VR . Frame |
|
100 m forest elements |
4,8 3-32 |
||
Elements from the board |
also |
1,4 0-97 |
|
Flooring with the fence |
100 m 2 flooring |
2,4 1-66 |
B. Installation and disassembly
The composition of the work
When installing forests
1. Installation of racks with laying linings on the ground or in ready-made pits, frustration and rubbing. 2. Installing elements of forests (subskings, battles, runs, fingers, etc.) and their mounting (nails, reinforcement, bolts, clamps, etc.). 3. Fishing racks before strengthening them with other elements. 4. Laying and fortification of flooring. 5. Installation of fences. 6. Lifting all the elements manually or block.
When disassembling forests
Disassembly with descent, sorting and stacking elements in the stack.
The composition of the link
A carpenter |
4 |
range |
- 1 |
" |
3 |
" |
- 1 |
" |
2 |
" |
- 2 |
table 2
Time norms and rates for the meters specified in the table
Forests are indigenous |
Meter |
Assembly and installation |
Disassembly |
|
Elements made of logs and plates |
100 m forest elements |
9,4 6-51 |
7,4 5-12 |
|
Elements from the board |
also |
7,8 5-40 |
5,1 3-53 |
|
Flooring with the fence |
100 m 2 flooring |
11 7-62 |
9,4 6-51 |
|
Note. The norms are provided by the height of the forests (from the ground to the upper flooring) 16 m.
§ E6-3. Scaffold
A. Summary batch, block and
Hinged-panel
The composition of the work
When installing (permuting) batch scope
1. Packet hook. 2. Installing packets in place. 3. Catching packages.
When installing (permuting) block scaffolds or inventory hinged and panel
Installation in the first position
1. Block hook. 2. Installing a block. 1. Catching block.
Installation in the second position
1. Block hook. 2. Lifting the block. 3. Sliding support frames. 4. Installing the block. 5. Capture block.
The composition of the link
Table 1
Time norms and rates for the meters specified in the table
Installation (permutation) of lumps |
Meter |
N.VR. Frame |
for |
||
machineist |
carpenters |
||||
Package |
1 package |
0,08 0-06 |
0,24 0-17,9 |
||
Block or hinged-panel |
in the first position |
1 block |
0,08 0-06 |
0,24 0-17,9 |
|
second position |
also |
0,07 0-05,2 |
0,21 0-15,6 |
||
B. Scatteries of other types
The composition of the work
When assembling inventory
1. Laying boards under the stands on the beams of overlapping or by flooring. 2. Installing racks or frames. 3. Checking the density of the installation of racks (or frames) on the flooring with a subcutation in the required places. 4. Check the placement and level of racks (or frames). 5. Laying, alignment and progressing. 6. Laying the flooring. 7. Sewing shields to runs. 8. Device of fences. 9. Laying of rolling strokes. 10. Device stepladder.
When disassembling inventory
1. Liberation of lobes from rolling strokes. 2. Removing fences. 3. Removal of flooring and sideboards, 4. Removing the stepladder. 5. Rewinding. 6. Cleaning racks or frames. 7. Relating all parts and stacking in the stack.
When assembling non-inventary scuffs
1. Marking of places of installation of supports. 2. Statution of racks with latch diagonal fights and workpiece. 3. Billet and laying of runs or fingers feeding to racks. 4. Laying of solid flooring with blank boards and feeding to runs or fingers. 5. Device fence. 6. Installation of stepladder.
When disassembling non-inventary scuffs
1. Removing fences. 2. Removing the floorboards. 3. Removing the stepladder. 4. Removing diagonal bouts. 5. Removing runs or fingers. 6. Relating all parts and stacked stack.
During the device flooring on the beams
1. Laying flooring on the beams backdrop or aims to the billet. 2. The feeding of each board in three places.
When disassembling flooring on the beams
1. Removing boards with pulling nails. 2. Referring to boards and stacking in the stack.
The composition of the link
A carpenter |
4 |
range |
- 1 |
" |
2 |
" |
- 1 |
Stuffing worker |
1 |
range |
- 1 |
table 2
Time norms and rates for 1 m Layout
Scaffold |
||||||
inventory |
non-inventar |
|||||
Name of works |
on racks with retractable rods or on ready-made frames (envelopes) |
on mobile tables, undergrings and ready-made goats |
on racks and runs with workpiece |
flooring over the labeling beams |
||
Assembly of lumps |
without moves |
0,14 0-09,4 |
0,08 0-05,4 |
0,16 0-10,8 |
0,07 0-04,7 |
|
0,15 0-10,1 |
0,18 0-12,1 |
0,09 0-06,1 |
||||
Disassembly of the thiefs |
without moves |
0,11 0-07,4 |
0,08 0-05,4 |
0,12 0-08,1 |
0,06 0-04 |
|
with strokes on the flooring on retaining racks or goats |
0,12 0-08,1 |
0,12 0-08,1 |
0,07 0-04,7 |
|||
Perestanovka |
without moves |
0,2 0-13,5 |
0,12 0-08,1 |
0,21 0-14,1 |
0,08 0-05,4 |
|
dumps within the floor |
with strokes on the flooring on retaining racks or goats |
0,22 0-14,8 |
0,23 0-15,5 |
0,1 0-06,7 |
||
Perestanovka |
without moves |
0,25 0-16,8 |
0,16 0-10,8 |
0,27 0-18,2 |
0,13 0-08,8 |
|
diameses with carrying to next-story |
with strokes on the flooring on retaining racks or goats |
0,27 0-18,2 |
0,29 0-19,5 |
0,16 0-10,8 |
||
Note. On the rise of 1 m 2 of the dimensions on the retractable rods with the plotting of the runs and dilation and the permutation of the flooring to add to each rise to the height of up to 0.8 m N. Ver. 0.12 people, h, Frame 0-08,1 (PR-1).
B. Scattering on metal racks
Normal instructions
Norms provide a solid loss device for finishing work In the rooms of the height of St. 4 m. The abilities are arranged on metal racks of inventory forests with the connection of elements by hinged clamps and steel wire.
The ability to consist of several tiers, every 2 m in height, the intermediate (mounting) flooring of shields with transits is satisfied. Racks are fused by connections. With the height of the submissions of St.6 M, except for the workshop, it is satisfied with a solid protective flooring. The rise of the elements of the lobes is done manually.
The composition of the work
When assembling a lump
1. The markup of the base for laying lining (lag) and the installation of the grooves. 2. Edit racks and connections. 3. Edit thread on bolts of hinged connections. 4. Cutting steel wire for spanning connections. 5. Billet linings (lag) and laying them on the base. 6. Installation of spyers on lining. 7. Installation of the 1st tier racks in the spyers. 8. Installation (extension) of racks for subsequent tiers. 9. Marking of the installation sites. 10. Installation of connections. 11. Installation of hinged clamps. 12. Installation shield installation device. 13. Device of the working floor. 14. Device of the protective flooring (at the height of lumps 6 m). 15. Pickup of metal elements of scuffs to a distance of up to 100 m. 16. Footage of wooden elements per distance up to 50 m.
The composition of the link
Installations for the installation of steel
and reinforced concrete structures:
4 |
range |
- 1 |
3 |
" |
- 2 |
2 |
" |
- 1 |
Table 3.
Time standards and rates for meters,
specified in the table
Name of works |
Meter |
N.VR. |
Frame |
||
Installation of the 1st tier with a height of 4 m |
0,31 |
0-21,9 |
|||
Installation follow-up |
also |
0,19 |
0-13,4 |
||
tiers high, m, to |
0,38 |
0-26,9 |
|||
Device working and protective flooring |
1 m 2 working or protective flooring |
0,11 |
0-07,8 |
With disassembly of the thiefs
1. Removing fences and stepladder. 2. Disassembly of the working and assembly floor. 3. Disassembling the protective flooring (at the height of lumps 6 m). 4. Removing hinged clamps and connections. 5. Removing the racks of the 1st and subsequent tiers and spyers. 6. Relating elements of losses (shields, racks, linings, scrubs, etc.) to a distance of up to 100 m.
The composition of the link
Installers for installation of steel and reinforced concrete structures:
4 |
range |
- 1 |
3 |
" |
- 2 |
2 |
" |
- 1 |
Table 4.
Time norms and rates for the meters specified in the table
Name of works |
Meter |
N.VR. |
Frame |
N. |
|
Disassembling the racks of the 1st tier with a height of 4 m |
1 m 2 Projections of lobes for the base |
0,2 |
0-14,2 |
1 |
|
Disassembling racks followed |
2 |
also |
0,12 |
0-08,5 |
2 |
tiers high, m, to |
4 |
" |
0,24 |
0-17 |
3 |
Disassembling working and protective flooring |
1 m 2 working or protective flooring |
0,07 |
0-05 |
4 |
§ E6-4. Step
The composition of the work
Under the device stepladder
1. Preparation of racks, markup, spikes and slot dumping. 2. Installing racks on lining. 3. Laying the guards and bonding them with stacks of brackets. 4. Fishing racks. 5. Laying of transverse crossbars in anticipation with nails sewing. 6. Outline of boards with sewing nails. 7 Priberation of Brucks on the flooring. 8. Installation of races railing and fastening them with railings. 9. Drain device.
When disassembling a stepladder
1. Removing the railing. 2. Removal of the flooring. 3. Removing the tents, dysproke, nozzles and racks. 4. Related materials and stacking.
The composition of the link
A carpenter |
4 |
range |
- 1 |
" |
2 |
" |
- 1 |
Stuffing worker |
1 |
range |
- 1 |
Time norms and rates for 1 m footpath
Type of stepladder |
Installation |
Disassembly |
|
On racks and asserts with the workpiece of all elements |
0,9 0-60,6 |
0,47 0-31,6 |
1 |
From ready-made shields |
0,49 0-33 |
0,19 0-12,8 |
2 |
but |
b. |
N. |
Note. The norms are provided by a ladder width of 1 m and over. With the width of the stepladder to 1 m N.VR. and Frame Multiply by 0.75 (PR-1).
Chapter 2. Assembling and device of wooden structures
Technical part
When calculating the volume of work performed follows:
calculation area is calculated on the area of \u200b\u200bits vertical projection, considering the height of the base from the marking of the planned land to the top of the drain board at the adjoining it to the wall;
the area of \u200b\u200bchopped walls is considered without deducting;
when determining the area of \u200b\u200bchopped walls, take: the length of the external walls along the outer knowledge; Length inland walls - between the outer edges of the outer walls; The height of the walls - between the upper face of the upper crown and the lower face of the bustling crown;
the area of \u200b\u200bpartitions of all types is calculated without deducting the openings, and the height of partitions - from the level of clean floor to the ceiling or to the top of the partitions, if the partitions are not brought to the ceiling;
when laying beams in the floors, the device of the spikes and warming of overlaps to calculate the overlap area in the light (between the capital walls) without deducting the area occupied by beams and furnaces.
§ E6-5. Foundations and socles
A. Foundations on pillars (chairs)
The composition of the work
1. Billet and assembly of chairs. 2. Antiseptation or firing. 3. Installing chairs in ready-made pits, catching over the cord and plumb. 4. Flipping holes and grinding ground around the chairs. 5. Align the top of the chairs in terms of the manufacture of spikes.
Table 1
Time norms and rates for 1 chair
The composition of the link |
Chair |
N.VR. |
Frame |
N. |
Carpenters: |
On crosses with pins |
3,1 |
2-15 |
1 |
4 Disma - 1. |
On litter with pins |
1,8 |
1-25 |
2 |
3 "- 1 |
On double liter without pins |
1,5 |
1-04 |
3 |
2 "- 2 |
On lining without podsov |
1 |
0-69,3 |
4 |
With the device Tambura
1. Floor outline with fit boards or boards. 2. Installing side shields with fastening. 3. The tambour roof device from shields with nails fastening. 4. Fit and hiding the entrance door of the tambour.
When appliance terraces and veranda
1. Overall and butterfit racks and open parts of the strapping. 2. Outlet of boards and bars. 3. Preparation of elements with a step. 4. Conjugation billet. 5. Figure Filovka. 6. Refecting the installation of the chairs. 7. Connection of strapping in the corners with mounting to chairs with nails. 8. Staying of boardy beams of two boards and struts, between beams with their feeding to the beams of nails. 9. Laying of floorboards with nails in each intersection with beams and with a fit of them in places connections with racks. 10. Installation of finished clean racks. 11. Laying the upper strapping on nails feeding. 12. Laying ceiling beams. 13. Installing rafting legs with a fit in places of adjustment to the upper strapping, with the strengthening of the other end to the wall of the house. 14. A clean carnis device with the installation of kills, feeding and connecting boards in the corners, with the lining of the lumps by the mare. 15. Ceiling cover on the beams.16. Dooming rafters with nails feeding boards. 17. Cleaning the base with clean boards. 18. Assembly and installation of fences from finished elements with strengthening. 19. Installation and strengthening of single deaf window bakes, fit and mounted light door cloths (with a veranda device).
Table 1
table 2
Designs |
Meter |
||||
Porch playground |
on the finished basis |
1 porch |
|||
with a base device |
|||||
1 step |
|||||
Two stands with their boards |
1 porch |
||||
Single trumps with wooden |
|||||
brackets and solid crate under |
|||||
clean with platforms and |
|||||
stringing hem |
|||||
Stairs |
caidial without bearing |
||||
the same, with a switcher |
|||||
Tambura entrance |
planed boards |
1 m2 floor |
|||
from three sides with |
|||||
adjoining the house of one |
|||||
side |
|||||
from three sides, under the finished |
|||||
common to the roof house |
|||||
Terraces open |
on both sides (with |
||||
attachment to the house two |
parties) |
||||
on the one hand with |
||||
attachment to the house three |
||||
parties |
||||
with an adjuncing to the house |
||||
one side |
||||
Veranda closed under the finished shared with the house |
||||
roof (with adjoining |
||||
house one side) |
||||
with an adjuncing to the house |
||||
two sides |
||||
with an adjuncing to the house |
||||
three sides |
Notes: 1. Line norms N 1 and 2, the device of the porker is up to 2.5 m2. With a larger area of \u200b\u200bthe porch for each 1 m2 add N. Ver. 1.4 people.-H, FRI. 1-04 (PR-1). 2. Under the device, the veranda of the workpiece of parts and the assembly of single deaf bindings and light doors is not provided and is charged additionally.
§ E6-13. Filling opening
The composition of the work
When installing blocks
1. Clearing the base of the opening. 2. Terminating block when tap is installed. 3. Block factory in the opening or installation along the laying in the design position. 4. Unimbilling the installation. 5. Swim block with blank wedges. 6. Fastening the block of a block to the wall of the rams.
When installing boxes
1. Cleaning the base of the opening from the frozen solution. 2. Installing the box with verification of the installation on the plumb and the level. 3. Fastening the box to the wall of the hershams.
When installing windows
1. Clearing the furrows (when installing window sills in stone walls). 2. A fit of the windows board at the place. 3. Applying antiseptic compositions and upholstery by felt. 4. Installation and level check. 5. Fastening the windows.
Add when installed on wooden brackets:
6. Production and installation of wooden brackets.
Add when installed on metal brackets:
6. Marking and dumping manually two sockets in the box of the window block (places of fastening metal brackets). 7. Installing brackets with fastening screws to the box.
When installing mounting boards
1. Cleaning the base of the opening of the frozen solution (when installed in stone walls). 2. Fit boards at the place. 3. Installing the mounting boards to the place with the trim and felt and the level reconciliation.
When the gate is hung
1. A fit of the gates of the goal in place. 2. The formulation of blacksmithing loops and hooks with drilling holes and fastening bolts. 3. Staging and strengthening grazing. 4. Hit the gate on the hook.
When the gate is hiding with the automotive crane
1. Marking of places for the installation of hooks (lylish). 2. Locking the goal sash. 3. Putting the gate sash in the openings. 4. Hit the gate of the gate on the hook. 5. Removing the correctness of the set of the gate.
At electric welding
1. Fastening the hooks to the electric welding box.
When setting metal squares
1. Marking and drilling holes. 2. Staging the bolts on bolts.
When having carpentry doors
1. Cliff and fit door cloths to the impeller. 2. Staging and strengthening loops on screws. 3. The setting of instruments and the doorway of the doors on the loop.
The composition of the link
A. For table. 1 rows N 2-7 and Table. 4 lines N 3 and 4
B. For Table 1 Rows N 1, Tables 2 and 3 (FULL); Table. 4 lines N 1, 2 and 7-11
Carpenter 4 breaks - one
" 2 " - 1
IN. For table. 4 lines N 5
Electric welder manual welding 3 raz. - one
G. for table. 4 lines N 6
Carpenter 3 breaks - one
A. Installation OKOHHHBIX and Door Blocks
Table 1
Time norms and rates for 100 m2 blocks of blocks (by outdoor vehicle)
Block area, |
With narrow single |
With wide or composite |
||
m2, BE |
boxes (with single or |
boxes (with two |
||
twisted binders) |
separate bindings) |
|||
N.VR. |
||||
machineist |
carpenters |
machineist |
carpenters |
B. Installation of boxes
table 2
Time norms and rates per 100 m 2 square of the box (by outdoor survey)
Window boxes |
Door boxes |
||||
boxes, m2, up |
|||||
wide or |
wide or |
||||
compound |
compound |
||||
B. Installation of subcast and mounting boards |
||||
Table 3. |
||||
Time norms and rates for the meters specified in the table |
||||
Meter |
||||
without brackets |
||||
Window boards on wooden brackets |
||||
on metal brackets |
||||
Mounting boards in the openings of industrial buildings |
Mr. Hit the gate and carpentry doors
Table 4.
Time norms and rates for the meters specified in the table
Meter |
||||||
Gate As |
single holders |
1 m2 of the canvas |
||||
installation |
||||||
double-spin |
||||||
Gate As |
for driver |
|||||
installation |
for carpenters |
|||||
fastening hooks and faces to |
1 Hook or |
|||||
box electric welding |
eye |
|||||
setting the angle of Obnik |
1 Galnik |
|||||
Carpentry |
on mortise |
single holders |
1 m2 of the canvas |
|||
knocks or B. |
||||||
tip |
double-spin |
|||||
on Plancks |
single holders |
|||||
double-spin |
||||||
on swinging loops |
Notes: 1. Na Dolbing two nests in the threshold for doorless boxes take 1 box N.VR. 0.13 people.-H, full 0-09.3 (PR-1). 2. Drying the bindings and door cloths in the box installed in the location in the table. 2 § E40-3-23 "Production of wooden structures and parts" with regard to paragraph 1 of the introductory part. 3. Table 1 standards of strings N 1 provides installation of blocks manually, and rows N 2-7 - crane. When installing blocks manually N.Ver. and all For carpenters of strings N 2-7 multiply by 1.7 (PR-2). Table 2 standards Installation of boxes are provided manually. 4. The production of work is provided at an altitude of up to 15 m from the ground level, in the production of work at the height of St. 15 m for each subsequent meter of the height of N.VR. and all Increase by 0.5% (PR-3). 5. Table stands. Figure 1 provides a tower crane or autocrante design, string standards N 3 and 4 Table 4 - only with a tower crane. When installing autocrante N.Ver. and all These lines are multiplied by 1.1 (PR-4). 6. When installing blocks into wooden walls without multipling the ridge on the ends of the simplicity of N. Ver. and all Table 1 Multiply 1.15 (PR-5). 7. The extension of the loaders of the log walls with finished parts of the deck and finished blocks with a ridge of the ridge on the ends of the sinks are normalized according to NOTE.2 § E6-6. 8. When installing blocks with glazed window bindings or door leafs N.VR. and all Table 1 Multiply to 1.15 (PR-6). 9. When installing unfolded blocks N. Ver. and all Table. 1 Multiply by 1.2 (PR-7). 10. On the removal from the loops of previously hung windows of non-beams, framug and doorbells with unscrewing loops, with a reverse sample of them and screwing the loops to take on 1 sash or Framuhu N. Ver. 0.12 people-h, FRI. 0-08.6 (PR-8); On 1 door leaf N.VR. 0.23 people. - H, FRI. 0-16.4 (PR-9). With removable hinges, take: on 1 sash or 1 fraamuga - N.VR. 0.04 people, hts. 0-02.9 (PR-10); on 1 doorbeal - N.VR 0.07 people.-H, FRI. 0-05 (PR-11). 11. The pantry of single and double boxes of dry packles is normalized by the collection of E8-1 "Finishing Works".
§ E6-14. Strike elements of filling openings
The composition of the work
1. Marking places squaling. 2. Removing the elements of filling the openings (door leaf, window sash, fraumuga or vectors) with loops. 3. Removing larvae, valves, cards, loops and forwarding (if necessary). 4. Stirring elements and fit at place. 5. Installation of larvae, valves, cards, loops and guidelines in place, partial recess of the sockets (if necessary). 6. Hitting the elements of the filling of openings.
Construction joiner - 5 disc. |
|||||
Time norms and rates for the meters specified in the table |
|||||
Meter |
|||||
Window blocks with selected |
|||||
binders at the opening area, m2, to |
|||||
Balcony door blocks with paired cloths |
|||||
Window Paired Framuga and Forms |
1 Framuga |
||||
at the area, m2, to |
or Fortochka |
||||
Window sash on removable and detachable |
1 sash |
||||
loops with separate bindings |
|||||
square, m2, up |
|||||
The same, on hinged loops (with |
|||||
unscrewing and screwing screws) |
|||||
at the sash area of \u200b\u200bfraumuga or |
|||||
footers, m2, up |
|||||
Door blocks at the area of \u200b\u200bopening, m2, up to |
|||||
Doors of built-in and antlesol wardrobes |
1 Polit |
||||
square, m2, up |
|||||
Notes: 1. By necessity Performing work on the shooting of elements of the filling of openings and the application of the appropriate standards of time and rates § E614 should be confirmed by the act approved by the head of the construction and installation (repair and construction) organization. 2. The standards of strings N 1-16 are provided for the staring of glazed elements of the opening of openings. In the staring of non-beam elements N.VR. and all These lines are multiplied by 0.85 (PR-1).
§ E6-15. Setting sealing cord
Time norms and rates for 1 m sealing cord
§ E6-16. Temporary filling window Operactions polyethylene film
The composition of the work
1. A framework of a frame with marking and pumping of bars. 2. Cutting with polyethylene film and frame covering. 3. Installing the frame in the opening and fastening it with nails.
Time standards and rates for 1 m perimeter opening
§ E6-17. Assembly and installation of built-in, attached and antlesol cabinets
Normal instructions
This paragraph provides for elemental standards for work on the device of built-in, attached and antlesol cabinets.
The time rate on the cabinet device of a particular design is defined as the sum of the corresponding elemental standards for execution necessary work With this cabinet.
Time norms and rates for the meters specified in the table
Name and composition of work |
The composition of the link |
Meter |
||||
stolyarov |
||||||
construction |
||||||
Installation, reconciliation and strengthening |
||||||
karkasov |
||||||
Installation and fastening of bars, |
1 m bars in |
|||||
supporting shelves, |
||||||
installation of referenceframes |
||||||
Installation |
dowels |
|||||
metal |
||||||
polkteroders |
||||||
with fastening |
shurupami |
|||||
Stacking shelves with fastening |
||||||
Setting and strengthening rods |
||||||
for clothes |
||||||
Installation Retifierlochboxes |
||||||
Installation |
built-in I. |
1 box |
||||
door boxes |
attached |
|||||
andresol |
||||||
Hitting the door |
built-in I. |
1 Polit |
||||
attached |
||||||
fastening |
||||||
loops screws |
andresol |
|||||
Installation |
built-in I. |
|||||
door blocks |
attached |
|||||
andresol |
||||||
Installation of finished shields |
||||||
Sewing of good and basement |
1 m Brousa |
|||||
Note. When hiding the door canvases, powered valuable breeds Tree, N.Vr. and all Rows N 10 and 11 multiplied by 1.25 (PR-1).
§ E6-18. Sealing wood-chip plate niche up to 2.7x0.6 m
The composition of the work
1. Installation and strengthening of bars to the walls of niche. 2. Singing niche wood-chipstones. 3. Sleet holes for passing pipelines.
Time rate and rates for 1 niche
Note. On the drilling in the walls of the nests, the manufacture and installation of traffic jams is added to each Tube N.VR. 0.21 people-h, FRI. 0-15 (PR-1).
§ E6-19. Installation of radiator fences
BUT. Fences lattice
B. Fences from chipboard
table 2
Time rate and rates for 1 m 2 fences
Note. The drilling of holes in chipboard and punching (drilling) in the walls of the cork sockets of § E6-19 are not taken into account and are increasing additionally.
§ E6-20. Installing cabinets for fire hoses
in concrete and Brick Walls
The composition of the work
1. Drilling the sockets to the plug in the plug. 2. Wooden plugging. 3. Installing cabinets in place and fixing screws.
§ E6-21. Installation refrigerated cabinets in niches of walls
The composition of the work
1. Clearing niche. 2. Installation and fastening of the cabinet. 3. The ranks of the gaps between the walls of the cabinet and the niche.
Time rate and rates for 1 cabinet
§ E6-22. Installation handrails
BUT. Wooden handrails on stair fences
a) with the workpiece of elements of the handrail
Table 1 |
||||||||||
When installing a straight part of the handrail |
In the manufacture of I. |
|||||||||
The composition of the link |
round I. |
figured |
staging |
|||||||
rectangular |
(symmetric I. |
roundings of all |
||||||||
sections (smooth) |
asymmetric) |
|||||||||
construction: |
||||||||||
Time norms and rates for the meters specified in the table |
||||||||||
Name and composition of work |
Meter |
Profile handrail |
||||||||
round I. |
figured |
|||||||||
rectangular |
(symmetric I. |
|||||||||
(smooth) |
asymmetric) |
|||||||||
Marking and repeat |
||||||||||
parts of the handrail, installation in place, |
||||||||||
fastening screws, sweeping and |
||||||||||
grinding |
||||||||||
Manufacture |
from march to march |
1 rounding |
||||||||
roundings |
||||||||||
installation on |
||||||||||
place, fit, |
from Marsha |
|||||||||
bonding I. |
playground or |
|||||||||
fastening |
end. |
|||||||||
scorouses |
||||||||||
cleaning I. |
straight Angle |
|||||||||
grinding |
playground |
|||||||||
roundings |
||||||||||
Connecting bruck |
1 rounding |
|||||||||
turning handrail without roundings. |
Putting the ends of the direct parts of the handrail, fitting the pairing and fastening the bar screw, clean turning with a stripping of the rashpil, fitting the champers and grinding Matchingeny
Note. The norms of the present table are provided by handrails and roundings of solid wood. When handrails and roundings of soft rocks N. Ver. and all Multiply by 0.7 (PR-1).
b) ready-made standard handrails |
||||
Stolar construction 3 solid. |
||||
Table 3. |
||||
The composition of the work |
||||
1. Installing handrails with learning (if necessary) |
||||
upper base fence. 2. Fastening the handrails |
B. Wooden handrails on balcony fences
The composition of the work
1. Marking of places of pairing with pinching "on the US". 2. Installing handrails in place with fastening their screws. 3. Stripping places of pairs.
Table 4.
Time rate and rates for 1 m handholdery
B. Polyvinyl chloride handrails
The composition of the work
1. Heated water and warming the handrails in hot water. 2. Cleaning and gauge of travelers. 3. Installing handrails. 4. Trimming the ends of the handrails.
Table 5. |
||||
Time norms and rates for 1 m handholdery |
||||
Name of works |
||||
construction |
||||
Installation of the direct part of the handrail with |
||||
hoping an end |
||||
Installing the handrail with simultaneous |
||||
rounding from march to march |